United States βΊ Grid βΊ Interconnection queues βΊ Illinois
ONSHORE WIND Β· PJMOnshore wind project AG1-121, Bureau County
Onshore wind project AG1-121, Bureau County is a 295 MW onshore wind request withdrawn in the PJM interconnection queue, in Bureau County, Illinois, connecting to ComEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2020 (completed)
- Withdrawn / abandonedJun 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-121
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Developer
- Leeward Renewable Energy Development, LLC
- Connection point (POI)
- Kewanee-Streator 138 kV
- Location
- Bureau County, Illinois
- Technology
- Wind: 295 MW
- Total requested
- 295 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 August 2020
- Proposed online date
- December 2024
- Withdrawn
- June 2024
Location
Marker shows the centre of Bureau County; the queue data does not give exact sites.
Other requests in Bureau County
- Bluejacket SolarSolar Β· 205 MW Β· in study
- Solar project J3944, Bureau CountySolar Β· 200 MW Β· in study
- Onshore wind project J1755, Bureau CountyOnshore wind Β· 147 MW Β· in study
- Onshore wind project AI2-487, Bureau CountyOnshore wind Β· 97.2 MW Β· in study
- Onshore wind project AI2-400, Bureau CountyOnshore wind Β· 25.0 MW Β· in study
- Big SkyOnshore wind Β· 240 MW Β· built
- Lone Tree WindOnshore wind Β· 79.4 MW Β· built
- Providence Heights WFOnshore wind Β· 74.0 MW Β· built
- Onshore wind project G561, Bureau CountyOnshore wind Β· 210 MW Β· withdrawn
- Walnut Ridge Wind FarmOnshore wind Β· 210 MW Β· withdrawn
- Onshore wind project R59, Bureau CountyOnshore wind Β· 160 MW Β· withdrawn
- Onshore wind project P21, Bureau CountyOnshore wind Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem