United States › Grid › Interconnection queues › Illinois
ONSHORE WIND · PJMWalnut Ridge Wind Farm
Walnut Ridge Wind Farm is a 210 MW onshore wind request withdrawn in the PJM interconnection queue, in Bureau County, Illinois, connecting to ComEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2005 (completed)
- Withdrawn / abandonedDec 2016 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- P20
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Nelson-Electric Junction 345kV
- Location
- Bureau County, Illinois
- Technology
- Wind: 210 MW
- Total requested
- 210 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 26 October 2005
- Proposed online date
- December 2017
- Withdrawn
- December 2016
Location
Marker shows the centre of Bureau County; the queue data does not give exact sites.
Other requests in Bureau County
- Bluejacket SolarSolar · 205 MW · in study
- Solar project J3944, Bureau CountySolar · 200 MW · in study
- Onshore wind project J1755, Bureau CountyOnshore wind · 147 MW · in study
- Onshore wind project AI2-487, Bureau CountyOnshore wind · 97.2 MW · in study
- Onshore wind project AI2-400, Bureau CountyOnshore wind · 25.0 MW · in study
- Big SkyOnshore wind · 240 MW · built
- Lone Tree WindOnshore wind · 79.4 MW · built
- Providence Heights WFOnshore wind · 74.0 MW · built
- Onshore wind project AG1-121, Bureau CountyOnshore wind · 295 MW · withdrawn
- Onshore wind project G561, Bureau CountyOnshore wind · 210 MW · withdrawn
- Onshore wind project R59, Bureau CountyOnshore wind · 160 MW · withdrawn
- Onshore wind project P21, Bureau CountyOnshore wind · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem