Requests shown31799.9 GW
Active in queue99.9 GW317 requests
Agreement signed12.2 GW66 requests
Withdrawn494132.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

317 requests Β· page 2 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 20, Sacramento County
Solar + storage
550 MWIn study Sacramento, CAWest Jul 2022target 2029
Solar + storage project G0753, Douglas County
Solar + storage
515 MWIn study Douglas, WAWest Jun 2022target 2025
Battery storage project C2-10, Salt Lake County
Battery storage Β· Oquirrh Energy Storage, LLC
500 MWAgreement signed Salt Lake, UTWest Apr 2022target 2031
Nuclear project C2-32, Lincoln County
Nuclear Β· US SFR Owner, LLC
500 MWAgreement signed Lincoln, WYWest Apr 2022target 2031
Solar + storage project Company PK, Esmeralda County
Solar + storage
500 MWIn study Esmeralda, NVWest Mar 2022target 2027
Solar + storage project Q89, Kern County
Solar + storage
500 MWIn study Kern, CAWest Apr 2022target 2027
Solar + storage project Company NP, Pershing County
Solar + storage
480 MWPaused / redesign Pershing, NVWest Mar 2022target 2030
Wind + storage project G0728, Sherman County
Wind + storage
420 MWIn study Sherman, ORWest Feb 2022target 2026
Battery storage project Company 212, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Solar + storage project 2023-G1
Solar + storage
400 MWIn study West Oct 2022target 2025
Solar + storage project G0744, Grant County
Solar + storage
400 MWIn study Grant, WAWest May 2022target 2026
Solar + storage project Company MW, White Pine County
Solar + storage
400 MWAgreement signed White Pine, NVWest Mar 2022target 2030
Onshore wind project C2-106, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest May 2022target 2025
Wind + storage project Company MX, Lyon County
Wind + storage
400 MWPaused / redesign Lyon, NVWest Mar 2022target 2027
Solar + storage project CLPT G21, Laramie County
Solar + storage
400 MWAgreement signed Laramie, WYWest Sep 2022target 2025
Solar + storage project Q486, Coconino County
Solar + storage
400 MWIn study Coconino, AZWest Sep 2022target 2027
Solar + storage project C2-203, Klamath County
Solar + storage
400 MWIn study Klamath, ORWest May 2022target 2025
Solar + storage project 667, Elmore County
Solar + storage Β· Martha Fields Energy Center, LLC
400 MWPaused / redesign Elmore, IDWest Aug 2022target 2029
Battery storage project Company 226, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Sep 2022target 2030
Solar + storage project 665, Ada County
Solar + storage Β· Blacks Creek Energy Center, LLC
400 MWAgreement signed Ada, IDWest Aug 2022target 2027
Solar + storage project G0732, Benton County
Solar + storage
400 MWIn study Benton, WAWest Mar 2022target 2027
Solar + storage project G0747, Klamath County
Solar + storage
400 MWIn study Klamath, ORWest Jun 2022target 2026
Solar + storage project Q480, Navajo County
Solar + storage
400 MWIn study Navajo, AZWest Sep 2022target 2025
Solar + storage project G0820, Douglas County
Solar + storage
400 MWIn study Douglas, WAWest Nov 2022target 2027
Solar + storage project GI-DISIS-2022-13, Prowers County
Solar + storage
398 MWAgreement signed Prowers, COWest May 2022target 2029
Battery storage project Company 228, Clark County
Battery storage
380 MWPaused / redesign Clark, NVWest Sep 2022target 2030
Solar + storage project CLPT G20, Laramie County
Solar + storage
365 MWAgreement signed Laramie, WYWest Jul 2022target 2025
Solar + storage project Company NB, White Pine County
Solar + storage
350 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Solar + storage project Company OA, Humboldt County
Solar + storage
350 MWPaused / redesign Humboldt, NVWest Sep 2022target 2030
Other project Q91, Los Angeles County
Other
346 MWIn study Los Angeles, CAWest Jun 2022target 2030
Battery storage project 696, Owyhee County
Battery storage Β· KCE ID 1, LLC
330 MWAgreement signed Owyhee, IDWest Dec 2022target 2026
Solar + storage project 655, Bear Lake County
Solar + storage Β· Aurora Solar LLC
325 MWPaused / redesign Bear Lake, IDWest May 2022target 2026
Solar + storage project G0817, Yakima County
Solar + storage
325 MWIn study Yakima, WAWest Oct 2022target 2025
Solar + storage project C2-208, Harney County
Solar + storage
320 MWIn study Harney, ORWest May 2022target 2027
Solar + storage project C2-152, Lake County
Solar + storage
320 MWIn study Lake, ORWest May 2022target 2028
Solar + storage project C2-182, Lake County
Solar + storage
320 MWIn study Lake, ORWest May 2022target 2029
Solar + storage project C2-187, Lake County
Solar + storage
320 MWIn study Lake, ORWest May 2022target 2029
Solar + storage project Q89, Pinal County
Solar + storage
313 MWIn study Pinal, AZWest Jan 2022target 2026
Battery storage project Company 213, Clark County
Battery storage
300 MWPaused / redesign Clark, NVWest Mar 2022target 2029
LA300W
Onshore wind
300 MWPaused / redesign Luna, NMWest Mar 2022target 2028
Solar + storage project C2-39, Iron County
Solar + storage
300 MWIn study Iron, UTWest Apr 2022target 2025
Solar + storage project Company MT, White Pine County
Solar + storage
300 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Solar + storage project Company 225, Clark County
Solar + storage
300 MWPaused / redesign Clark, NVWest Sep 2022target 2030
Solar + storage project 145, Cochise County
Solar + storage
300 MWIn study Cochise, AZWest Dec 2022target 2025
Solar + storage project Q465, Maricopa County
Solar + storage
300 MWIn study Maricopa, AZWest Mar 2022target 2025
Other project CLPT G17, Laramie County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Laramie, WYWest Apr 2022target 2025
Battery storage project 632, Owyhee County
Battery storage Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Owyhee, IDWest Jan 2022target 2025
Solar + storage project C2-72, Tooele County
Solar + storage
300 MWIn study Tooele, UTWest May 2022target 2025
Battery storage project Q467, Maricopa County
Battery storage
300 MWIn study Maricopa, AZWest Mar 2022target 2026
Solar + storage project 2022-G9, Pinal County
Solar + storage
300 MWIn study Pinal, AZWest Jul 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)