United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in SPP (Southwest Power Pool) — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown21237.6 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

212 requests · page 2 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2018-125, Lancaster County
Onshore wind
231 MWAgreement signed Lancaster, NESPP Nov 2018target 2031
Solar project GEN-2021-049, Lancaster County
Solar
225 MWAgreement signed Lancaster, NESPP Apr 2021target 2029
Solar + storage project GEN-2020-079, Cherokee County
Solar + storage
225 MWAgreement signed Cherokee, KSSPP Apr 2020target 2028
Solar project GEN-2018-131, Pierce County
Solar
221 MWAgreement signed Pierce, NESPP Nov 2018target 2031
Onshore wind project GEN-2015-066, Pawnee County
Onshore wind
220 MWAgreement signed Pawnee, OKSPP Oct 20152025
Onshore wind project GEN-2017-233, Grady County
Onshore wind
215 MWAgreement signed Grady, OKSPP Nov 2017target 2027
Onshore wind project GEN-2018-082, Pittsburg County
Onshore wind
215 MWAgreement signed Pittsburg, OKSPP Nov 2018target 2030
Battery storage project GEN-2019-011, Yoakum County
Battery storage
207 MWAgreement signed Yoakum, TXSPP Apr 2019target 2028
Solar project GEN-2021-033, Franklin County
Solar
204 MWAgreement signed Franklin, ARSPP May 2021target 2028
Solar project GEN-2021-036, Little River County
Solar
204 MWAgreement signed Little River, ARSPP May 2021target 2027
Solar project GEN-2018-057, Sedgwick County
Solar
203 MWAgreement signed Sedgwick, KSSPP May 2018target 2030
Onshore wind project GEN-2016-004, Oliver County
Onshore wind
202 MWAgreement signed Oliver, NDSPP Mar 2016target 2027
Solar project GEN-2018-132, Pierce County
Solar
202 MWAgreement signed Pierce, NESPP Nov 2018target 2026
Solar + storage project GEN-2020-020, Mccurtain County
Solar + storage
202 MWAgreement signed Mccurtain, OKSPP Apr 2020target 2027
Onshore wind project GEN-2017-004, Cloud County
Onshore wind
202 MWAgreement signed Cloud, KSSPP Apr 2017target 2027
Solar project GEN-2017-226, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Battery storage project GEN-2017-227, Sedgwick County
Battery storage
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Solar project GEN-2017-220, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2026
Onshore wind project GEN-2018-128, Sumner County
Onshore wind
200 MWAgreement signed Sumner, KSSPP Nov 2018target 2030
Solar project GEN-2017-040, Ochiltree County
Solar
200 MWAgreement signed Ochiltree, TXSPP May 2017target 2026
Battery storage project GEN-2020-081, Rusk County
Battery storage
200 MWAgreement signed Rusk, TXSPP Apr 2020target 2028
Solar project GEN-2017-075, Johnston County
Solar
200 MWAgreement signed Johnston, OKSPP May 2017target 2026
Onshore wind project GEN-2017-121, Sumner County
Onshore wind
200 MWAgreement signed Sumner, KSSPP Nov 2017target 2026
Battery storage project GEN-2024-SR11, Garfield County
Battery storage
200 MWAgreement signed Garfield, OKSPP May 20242025
Solar project GEN-2019-016, Polk County
Solar
200 MWAgreement signed Polk, MOSPP Apr 2019target 2029
Battery storage project GEN-2023-SR8, Hansford County
Battery storage
200 MWAgreement signed Hansford, TXSPP Feb 2023target 2026
Battery storage project GEN-2019-012, Woodward County
Battery storage
200 MWAgreement signed Woodward, OKSPP May 2019target 2027
Battery storage project GEN-2018-028, Tulsa County
Battery storage
200 MWAgreement signed Tulsa, OKSPP May 2018target 2028
Onshore wind project GEN-2017-144, Holt County
Onshore wind
200 MWAgreement signed Holt, NESPP Nov 2017target 2028
Solar project GEN-2018-050, Caddo Parish County
Solar
200 MWAgreement signed Caddo Parish, LASPP May 2018target 2028
Onshore wind project GEN-2017-133, Oklahoma County
Onshore wind
200 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Solar project GEN-2017-092, Muskogee County
Solar
200 MWAgreement signed Muskogee, OKSPP May 2017target 2026
Onshore wind project GEN-2016-074, Custer County
Onshore wind
200 MWAgreement signed Custer, NESPP Apr 2016target 2027
Onshore wind project GEN-2018-089, Castro County
Onshore wind
196 MWAgreement signed Castro, TXSPP Nov 2018target 2028
Solar project GEN-2017-018, Barber County
Solar
189 MWAgreement signed Barber, KSSPP May 20172025
Onshore wind project GEN-2016-133, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-134, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-138, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-137, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2017-119, Cloud County
Onshore wind
180 MWAgreement signed Cloud, KSSPP Nov 2017target 2027
Onshore wind project GEN-2017-222, Crawford County
Onshore wind
180 MWAgreement signed Crawford, IASPP Nov 2017target 2027
Battery storage project GEN-2024-SR5, Creek County
Battery storage
177 MWAgreement signed Creek, OKSPP Feb 2024target 2026
Onshore wind project GEN-2016-128, Alfalfa County
Onshore wind
176 MWAgreement signed Alfalfa, OKSPP Nov 2016target 2026
Onshore wind project GEN-2011-019, Woodward County
Onshore wind
175 MWAgreement signed Woodward, OKSPP Mar 2011target 2027
Onshore wind project GEN-2016-146, Texas County
Onshore wind
175 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-145, Texas County
Onshore wind
175 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Solar project GEN-2019-039, Butler County
Solar
175 MWAgreement signed Butler, NESPP May 2019target 2027
Battery storage project GEN-2023-SR4, Burke County
Battery storage
170 MWAgreement signed Burke, NDSPP Dec 2022target 2026
Onshore wind project GEN-2011-020, Ellis County
Onshore wind
166 MWAgreement signed Ellis, OKSPP Mar 2011target 2027
Solar project GEN-2018-106, Caddo Parish County
Solar
165 MWAgreement signed Caddo Parish, LASPP Nov 2018target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)