Queue requests in study in PJM (Mid-Atlantic, Midwest) — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown905105.4 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

905 requests · page 2 of 19
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AI1-024, Mclean County
Battery storage
300 MWIn study Mclean, ILPJM Apr 2022target 2026
Battery storage project AH1-260, Camden County
Battery storage · Haddy Energy Storage LLC
300 MWIn study Camden, NJPJM Jan 2025target 2025
Solar + storage project AI2-443, Greene County
Solar + storage
300 MWIn study Greene, PAPJM Mar 2023target 2027
Steward Creek Solar
Solar · Steward Creek Solar, LLC
300 MWIn study Lee, ILPJM Dec 2019target 2023
Dawson Solar
Solar · Deriva Energy Solar, LLC
300 MWIn study Mclean, ILPJM Sep 2020target 2024
Battery storage project AI1-017, Surry County
Battery storage
300 MWIn study Surry, VAPJM Apr 2022target 2026
Battery storage project AH2-334, Camden County
Battery storage
300 MWIn study Camden, NJPJM Mar 2022target 2025
Battery storage project AH2-415, Livingston County
Battery storage
300 MWIn study Livingston, ILPJM Mar 2022target 2026
Burr Oak Solar
Solar · Leeward Renewable Energy Development, LLC
300 MWIn study Dekalb, ILPJM Aug 2020target 2023
Three Lakes Solar
Solar + storage · Three Lakes Solar LLC
300 MWIn study St. Joseph, MIPJM Sep 2019target 2022
South Dixon Solar
Solar · Deriva Energy Solar, LLC
300 MWIn study Lee, ILPJM Mar 2020target 2022
Solar project AG2-363, Tazewell County
Solar · Mackinaw Solar LLC
300 MWIn study Tazewell, ILPJM Mar 2025target 2024
Battery storage project AI1-018, Spotsylvania County
Battery storage
300 MWIn study Spotsylvania, VAPJM Apr 2022target 2026
Black Diamond Solar
Solar · Black Diamond Solar Power, LLC
299 MWIn study Christian, ILPJM Mar 2019target 2022
Solar project AI1-085, Wayne County
Solar
290 MWIn study Wayne, INPJM Jul 2022target 2030
Solar project AH2-322, Pittsylvania County
Solar
290 MWIn study Pittsylvania, VAPJM Mar 2022target 2025
Battery storage project AI1-187, Hunterdon County
Battery storage
280 MWIn study Hunterdon, NJPJM Sep 2022target 2027
Solar project AG2-453, Kendall County
Solar · Fox Valley Energy Facility, LLC
280 MWIn study Kendall, ILPJM Feb 2025target 2024
Solar project AH2-342, Stark County
Solar
280 MWIn study Stark, ILPJM Mar 2022target 2027
Solar project AI2-081, Logan County
Solar
271 MWIn study Logan, OHPJM Feb 2023target 2025
Gas project AH1-734, Indiana County
Gas · Armstrong Power, LLC
270 MWIn study Indiana, PAPJM Apr 2025
Beacon Solar
Solar · Beacon Solar, LLC
260 MWIn study Rock Island, ILPJM Sep 2020target 2023
Battery storage project AJ1-014, Will County
Battery storage
260 MWIn study Will, ILPJM May 2023target 2027
Nuclear project AH1-710, Salem County
Nuclear · PSEG Nuclear LLC
257 MWIn study Salem, NJPJM Apr 2025
Livingston Wind
Onshore wind · Livingston Wind Project, LLC
255 MWIn study Livingston, ILPJM Sep 2018target 2021
Vermilion Grove Wind
Onshore wind · Vermilion Grove Wind, LLC
255 MWIn study Vermillion, INPJM Sep 2019target 2022
Gipper Solar Farm
Solar · Gipper Solar Farm, LLC
255 MWIn study Whiteside, ILPJM Oct 2020target 2023
Solar project AI1-040, Elk County
Solar
250 MWIn study Elk, PAPJM Apr 2022target 2025
Solar + storage project AH2-112, St. Joseph County
Solar + storage
250 MWIn study St. Joseph, INPJM Feb 2022target 2026
Battery storage project AI1-149, Mchenry County
Battery storage
250 MWIn study Mchenry, ILPJM Sep 2022target 2025
Battery storage project AI2-068, Monmouth County
Battery storage
250 MWIn study Monmouth, NJPJM Feb 2023target 2026
Battery storage project AJ1-013, Will County
Battery storage
250 MWIn study Will, ILPJM May 2023target 2027
Solar + storage project AI1-172, Grundy County
Solar + storage
250 MWIn study Grundy, ILPJM Sep 2022target 2028
Battery storage project AI1-167, Clermont County
Battery storage
250 MWIn study Clermont, OHPJM Sep 2022target 2028
Solar project AH2-069, Wythe County
Solar
250 MWIn study Wythe, VAPJM Jan 2022target 2025
Battery storage project AG2-360, Smyth County
Battery storage · Laurel Creek Energy Storage LLC
250 MWIn study Smyth, VAPJM Feb 2025target 2024
Battery storage project AI2-069, Monmouth County
Battery storage
250 MWIn study Monmouth, NJPJM Feb 2023target 2026
Solar project AG2-029, Noble County
Solar · Southern Pike Solar LLC
250 MWIn study Noble, INPJM Feb 2025target 2024
Solar project AG2-163, Fountain County
Solar · Dolphin Solar LLC
250 MWIn study Fountain, INPJM Feb 2025target 2024
Solar + storage project AH2-113, Livingston County
Solar + storage
250 MWIn study Livingston, ILPJM Feb 2022target 2026
Maryland Offshore Wind Energy Project (MOWEP)
Offshore wind
248 MWPaused / redesign Sussex, DEPJM Aug 2015target 2027
Battery storage project AI1-154, Will County
Battery storage
230 MWIn study Will, ILPJM Sep 2022target 2027
Battery storage project AH2-421, Grundy County
Battery storage
230 MWIn study Grundy, ILPJM Mar 2022target 2025
Solar project AH1-055, Jackson County
Solar · Furnace Solar, LLC
220 MWIn study Jackson, OHPJM Feb 2025target 2026
Solar project AG2-245, Starke County
Solar · STARKE CENTRAL PROJECT, LLC
210 MWIn study Starke, INPJM Mar 2025target 2023
Battery storage project AI1-185, Augusta County
Battery storage
210 MWIn study Augusta, VAPJM Sep 2022target 2027
Solar project AG2-184, Knott County
Solar · STMO bn, LLC
210 MWIn study Knott, KYPJM Feb 2025target 2024
Solar + storage project AH2-419, Laporte County
Solar + storage
210 MWIn study Laporte, INPJM Mar 2022target 2026
Broomstick Solar Energy Centergy Center
Solar
210 MWPaused / redesign Christian, ILPJM Mar 2018target 2028
Fountain Point Solar
Solar · Fountain Point Solar Energy LLC
207 MWIn study Union, OHPJM Aug 2018target 2021
Page 2 of 19

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)