United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 190

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 190 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AG2-304, Prince William County
Battery storage · Urban Grid Solar Projects, LLC
150 MWWithdrawn / abandoned Prince William, VAPJM Jan 2025target 2023
Onshore wind project J840, Humboldt County
Onshore wind
150 MWWithdrawn / abandoned Humboldt, IAMISO Jun 2017target 2021
Onshore wind project 175, Lincoln County
Onshore wind
150 MWWithdrawn / abandoned Lincoln, WYWest Dec 2007target 2011
Dean Wind
Onshore wind · Gamesa Energy USA, LLC
150 MWWithdrawn / abandoned Tioga, NYNYISO Dec 2006
Solar + storage project AF1-279, Lorain County
Solar + storage
150 MWWithdrawn / abandoned Lorain, OHPJM Sep 2019target 2022
Onshore wind project G0315, Lewis County
Onshore wind
150 MWWithdrawn / abandoned Lewis, WAWest Mar 2008target 2012
Battery storage project Company PZ, Storey County
Battery storage
150 MWWithdrawn / abandoned Storey, NVWest Mar 2023target 2027
Eureka Flats Wind Farm
Onshore wind · Winds Over Washington Energy Group
150 MWWithdrawn / abandoned Whatcom, WAWest Oct 2001target 2004
King Mt II
Solar · Nextera
150 MWWithdrawn / abandoned ERCOT Sep 2014target 2016
Onshore wind project J111, Mower County
Onshore wind
150 MWWithdrawn / abandoned Mower, MNMISO Jan 2010target 2012
Onshore wind project 43, Adams County
Onshore wind
150 MWWithdrawn / abandoned Adams, WAWest Dec 2014target 2016
Silverline Energy Center
Solar + storage · Silverline Energy Center, LLC
150 MWWithdrawn / abandoned Tompkins, NYNYISO Sep 2024
Onshore wind project J751, Adams County
Onshore wind
150 MWWithdrawn / abandoned Adams, ILMISO Nov 2016target 2019
Onshore wind project J297, O'brien County
Onshore wind
150 MWWithdrawn / abandoned O'brien, IAMISO Oct 2013
Solar + storage project G0746, Benton County
Solar + storage
150 MWWithdrawn / abandoned Benton, WAWest May 2022target 2025
Onshore wind project J008, Knox County
Onshore wind
150 MWWithdrawn / abandoned Knox, ILMISO Oct 2008target 2010
Solar project AE2-050, Will County
Solar
150 MWWithdrawn / abandoned Will, ILPJM Jan 2019target 2021
Battery storage project AG1-020, Loudoun County
Battery storage
150 MWWithdrawn / abandoned Loudoun, VAPJM May 2020target 2023
Battery storage project AG2-285, Loudoun County
Battery storage
150 MWWithdrawn / abandoned Loudoun, VAPJM Mar 2021target 2023
Solar project IC-1189, Marion County
Solar
150 MWWithdrawn / abandoned Marion, GASoutheast Oct 2023target 2028
Onshore wind project 12, Kittitas County
Onshore wind
150 MWWithdrawn / abandoned Kittitas, WAWest Jun 2007target 2008
Solar project AF2-216, Union County
Solar
150 MWWithdrawn / abandoned Union, OHPJM Mar 2020target 2024
Onshore wind project GI-0308, Codington County
Onshore wind
150 MWWithdrawn / abandoned Codington, SDWest Apr 2003
Battery storage project 372, Deer Lodge County
Battery storage
150 MWWithdrawn / abandoned Deer Lodge, MTWest Jan 2020target 2022
Solar + storage project 25-IC-1341, Greene County
Solar + storage
150 MWWithdrawn / abandoned Greene, GASoutheast Apr 2025
Solar project IC-767, Shelby County
Solar
150 MWWithdrawn / abandoned Shelby, ALSoutheast Dec 2018target 2022
Solar project AH1-437, Culpeper County
Solar
150 MWWithdrawn / abandoned Culpeper, VAPJM Sep 2021target 2026
Solar project Q201, Maricopa County
Solar
150 MWWithdrawn / abandoned Maricopa, AZWest Jun 2011target 2014
Onshore wind project AD2-150, Dekalb County
Onshore wind
150 MWWithdrawn / abandoned Dekalb, ILPJM Mar 2018target 2020
Battery storage project GEN-2022-135, Lea County
Battery storage
150 MWWithdrawn / abandoned Lea, NMSPP Feb 2023target 2027
Solar project J2432, Tunica County
Solar
150 MWWithdrawn / abandoned Tunica, MSMISO Sep 2022target 2026
Onshore wind project G0233, Klickitat County
Onshore wind
150 MWWithdrawn / abandoned Klickitat, WAWest Sep 2006target 2007
Battery storage project C3-135, Utah County
Battery storage
150 MWWithdrawn / abandoned Utah, UTWest May 2023target 2027
Cuerno Grande Wind
Onshore wind
150 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2035
Onshore wind project GI-0619, Dickey County
Onshore wind
150 MWWithdrawn / abandoned Dickey, NDWest Dec 2006target 2010
Solar project AG1-075, Greensville County
Solar · Jarratt Solar, LLC
150 MWWithdrawn / abandoned Greensville, VAPJM Jul 2020target 2024
Onshore wind project GEN-2009-009, Barton County
Onshore wind
150 MWWithdrawn / abandoned Barton, KSSPP Mar 2009target 2011
Battery storage project 25-IC-AU
Battery storage
150 MWWithdrawn / abandoned GASoutheast
Windcharger ESS
Battery storage
150 MWWithdrawn / abandoned Solano, CACAISO Apr 2018target 2021
Battery storage project AH1-579, Union County
Battery storage
150 MWWithdrawn / abandoned Union, OHPJM Sep 2021target 2028
Onshore wind project AD2-137, Will County
Onshore wind
150 MWWithdrawn / abandoned Will, ILPJM Mar 2018target 2020
Battery storage project AG2-319, Anne Arundel County
Battery storage
150 MWWithdrawn / abandoned Anne Arundel, MDPJM Mar 2021target 2025
Solar project 20230823001, Colleton County
Solar
150 MWWithdrawn / abandoned Colleton, SCSoutheast target 2026
Onshore wind project GEN-2020-SR4, Ford County
Onshore wind
150 MWWithdrawn / abandoned Ford, KSSPP Aug 20202021
Other project 151, Pima County
Other
150 MWWithdrawn / abandoned Pima, AZWest Mar 2023target 2026
Onshore wind project J3332, Calumet County
Onshore wind
150 MWWithdrawn / abandoned Calumet, WIMISO Apr 2024target 2028
Solar project J1689, Henry County
Solar
150 MWWithdrawn / abandoned Henry, INMISO Jun 2020target 2023
Battery storage project C2-157, Walla Walla County
Battery storage
150 MWWithdrawn / abandoned Walla Walla, WAWest May 2022target 2025
Solar project AG2-580, Brunswick County
Solar · Bellflower Holdings, LLC
150 MWWithdrawn / abandoned Brunswick, VAPJM Jan 2021target 2024
Solar project 325, Lowndes County
Solar
150 MWWithdrawn / abandoned Lowndes, MSSoutheast Aug 2017
Page 190 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)