Onshore wind project 43, Adams County

Onshore wind project 43, Adams County is a 150 MW onshore wind request withdrawn in the West interconnection queue, in Adams County, Washington, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2014 (completed)
  2. Withdrawn / abandonedDec 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
43
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
A 115 kV interconnection Near Lind 115 kV Substation
Location
Adams County, Washington
Technology
Wind: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
15 December 2014
Proposed online date
December 2016
Withdrawn
December 2015

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.