Solar + storage project Q59, Adams County

Solar + storage project Q59, Adams County is a 60.0 MW solar + storage request suspended in the West interconnection queue, in Adams County, Washington, connecting to Avista Utilities.

Queue statusPaused / redesign
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q59
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Roxboro 115kV Station
Location
Adams County, Washington
Technology
Solar: 60.0 MW · Battery
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
Request Status: Suspended; Facilities Study: Complete; Phase One Cluster Study: Feasibility; Phase One Re-Study: N/A; Ph
Queue status
Suspended

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem