Solar project CS24-01, Adams County

Solar project CS24-01, Adams County is a 1.0 MW solar request with a signed interconnection agreement in the West interconnection queue, in Adams County, Washington, connecting to Avista Utilities.

Queue statusConsented
  1. PlanningQueued Mar 2024 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
CS24-01
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
S. Othello 13kV
Location
Adams County, Washington
Technology
Solar: 1.0 MW
Total requested
1.0 MW
Service type
Network resource (NRIS)
Study phase
Request Status: SGIA; Facilities Study: N/A; Phase One Cluster Study: Complete; Phase One Re-Study: N/A; Phase Two Clust
Queue status
Active
Entered queue
26 March 2024
Proposed online date
November 2024

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem