Onshore wind project 175, Lincoln County

Onshore wind project 175, Lincoln County is a 150 MW onshore wind request withdrawn in the West interconnection queue, in Lincoln County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2007 (completed)
  2. Withdrawn / abandonedFeb 2014 (project stopped here)
  3. ConsentedNov 2009 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
175
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Craven Creek substation
Location
Lincoln County, Wyoming
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
IA signed 11/24/09, Suspended 2/15/11, Terminated 2/17/14
Queue status
Withdrawn
Entered queue
7 December 2007
Agreement signed
24 November 2009
Proposed online date
October 2011
Withdrawn
February 2014

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem