United States › Grid › Interconnection queues › Wyoming

SOLAR · WEST

Solar project 974, Lincoln County

Solar project 974, Lincoln County is a 80.0 MW solar request suspended in the West interconnection queue, in Lincoln County, Wyoming, connecting to PacifiCorp.

Queue statusPaused / redesign
  1. PlanningQueued Nov 2017 (current stage)
  2. ConsentedSep 2020 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
974
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Lincoln Solar, LLC
Connection point (POI)
Naughton-Treasureton transmission line
Location
Lincoln County, Wyoming
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
IA executed 9/14/2020, suspended 11/29/23
Queue status
Suspended
Entered queue
15 November 2017
Agreement signed
14 September 2020
Proposed online date
July 2024

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Wyoming · Transmission lines in Wyoming

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem