πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

BATTERY STORAGE Β· SOUTHEAST

Battery storage project 25-IC-AU

Battery storage project 25-IC-AU is a 150 MW battery storage request withdrawn in the Southeast interconnection queue, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedApr 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25-IC-AU
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Thalmann - Duval 500 kV Line
Location
Georgia
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Withdrawn
April 2025

Location

No county location in the queue data.

Power plants in Georgia Β· Transmission lines in Georgia

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem