🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA (2023 requests) — page 18

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,065262.8 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,065 requests · page 18 of 22
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 529, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2029
Solar project 536, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 566, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2032
Solar project 491, Indian River County
Solar · FPL
74.5 MWIn study Indian River, FLSoutheast Jan 2023target 2028
Solar project 569, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2031
Solar project 537, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 101, Hillsborough County
Solar
74.5 MWIn study Hillsborough, FLSoutheast Apr 2023target 2025
Solar project 510, Manatee County
Solar · FPL
74.5 MWIn study Manatee, FLSoutheast Jan 2023target 2030
Solar project 568, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2031
Solar project 565, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2032
Battery storage project GEN-2023-SR25, Mayes County
Battery storage
72.5 MWIn study Mayes, OKSPP Jul 20232024
Battery storage project GEN-2023-SR26, Mayes County
Battery storage
72.5 MWIn study Mayes, OKSPP Jul 20232024
Solar project AI2-409, Dekalb County
Solar
72.0 MWIn study Dekalb, ILPJM Mar 2023target 2026
Solar project AI2-164, Wood County
Solar
72.0 MWIn study Wood, OHPJM Mar 2023target 2025
Pato Blanco Storage
Battery storage · TX BESS 4, LLC
71.3 MWIn study Fort Bend, TXERCOT May 2023target 2026
Edens Solar
Solar · Hill PV, LLC
70.4 MWIn study Hill, TXERCOT Oct 2023target 2027
Gas project AJ1-023, Trumbull County
Gas
70.0 MWIn study Trumbull, OHPJM Jun 2023target 2024
Battery storage project Q518, Yuma County
Battery storage
70.0 MWIn study Yuma, AZWest Mar 2023target 2023
Battery storage project AI2-052, Ocean County
Battery storage
70.0 MWIn study Ocean, NJPJM Feb 2023target 2027
Solar project G1010, Yakima County
Solar
70.0 MWIn study Yakima, WAWest Nov 2023target 2027
Solar project 920651, Darlington County
Solar
70.0 MWIn study Darlington, SCSoutheast Sep 2023
Solar project AI2-358, Van Buren County
Solar
70.0 MWIn study Van Buren, MIPJM Mar 2023target 2028
Solar project AI2-195, Lycoming County
Solar
69.9 MWIn study Lycoming, PAPJM Mar 2023target 2025
Off Stream Water Storage
Battery storage
68.9 MWIn study Colusa, CACAISO Apr 2023target 2030
Onshore wind project AI2-163, Mclean County
Onshore wind
68.8 MWIn study Mclean, ILPJM Mar 2023target 2025
Solar project IC-1176, Glascock County
Solar
68.5 MWPaused / redesign Glascock, GASoutheast Sep 2023target 2028
Onshore wind project G1012, Umatilla County
Onshore wind
67.0 MWIn study Umatilla, ORWest Nov 2023target 2030
Solar project 915787, Florence County
Solar
65.0 MWIn study Florence, SCSoutheast Sep 2023
Solar project 915773, Dillon County
Solar
65.0 MWIn study Dillon, SCSoutheast Sep 2023
Solar project 917739, Marion County
Solar
63.9 MWIn study Marion, SCSoutheast Sep 2023
Box
Solar
63.4 MWIn study Riverside, CACAISO Apr 2023target 2029
Little Hill
Battery storage
63.1 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Solar project 336, Gilchrist County
Solar · Seminole Electric Cooperative, Inc
61.2 MWPaused / redesign Gilchrist, FLSoutheast Sep 2023target 2028
Battery storage project AI2-307, Cecil County
Battery storage
60.5 MWIn study Cecil, MDPJM Mar 2023target 2026
Indigo Storage 4
Solar + storage · Innovative Solar 245, LLC
60.0 MWIn study Fisher, TXERCOT Oct 2023target 2026
Indigo Storage 2
Solar + storage · Innovative Solar 245, LLC
60.0 MWIn study Fisher, TXERCOT Sep 2023target 2026
Solar + storage project Q534, Navajo County
Solar + storage
60.0 MWIn study Navajo, AZWest Apr 2023target 2026
Onshore wind project S0023, Fort Bridger County
Onshore wind
60.0 MWIn study Fort Bridger, WYWest Nov 2023target 2027
Battery storage project AI2-231A, Botetourt County
Battery storage
60.0 MWIn study Botetourt, VAPJM Mar 2023target 2023
Indigo Storage 3
Solar + storage · Innovative Solar 245, LLC
60.0 MWIn study Fisher, TXERCOT Nov 2023target 2026
Solar + storage project AI2-444
Solar + storage
59.5 MWIn study WVPJM Mar 2023target 2026
Solar project AI2-245, Woodford County
Solar
55.2 MWIn study Woodford, ILPJM Mar 2023target 2028
Solar project AI2-224, Charlotte County
Solar
55.0 MWIn study Charlotte, VAPJM Mar 2023target 2025
Solar project 239, Marion County
Solar
55.0 MWIn study Marion, SCSoutheast Jun 2023target 2027
Solar project GEN-2023-135, Bowie County
Solar
52.0 MWIn study Bowie, TXSPP Oct 2023target 2026
Orchard Ray BESS
Battery storage · Pettus BESS
51.9 MWIn study Bee, TXERCOT Jun 2023target 2027
Solar project AI2-196, Lycoming County
Solar
51.5 MWIn study Lycoming, PAPJM Mar 2023target 2025
Proving Ground BESS
Solar + storage · Lantana Solar LLC
51.4 MWIn study Schleicher, TXERCOT Jul 2023target 2028
Solar project Q104, Pinal County
Solar
51.3 MWIn study Pinal, AZWest May 2023target 2025
Ayass BESS
Battery storage · Harvick BESS, LLC
51.3 MWIn study Throckmorton, TXERCOT Dec 2023target 2028
Page 18 of 22

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)