United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Texas — page 17

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,486351.5 GW
Active in queue476.4 GW2,094 requests
Agreement signed124.6 GW606 requests
Withdrawn917184.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,486 requests · page 17 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Monument Hill Solar
Solar · RWE Solar Development, LLC
200 MWIn study Fayette, TXERCOT Oct 2023target 2027
Tierra Blanca W
Onshore wind · RWE Renewables Development, LLC
200 MWPaused / redesign Randall, TXERCOT Sep 2013target 2021
Battery storage project GEN-2024-355, Lubbock County
Battery storage
199 MWIn study Lubbock, TXSPP Mar 2025target 2030
Wi-Al2-199SB
Solar + storage
199 MWIn study El Paso, TXWest Jun 2025target 2029
Wi-Al3-199SB
Solar + storage
199 MWIn study El Paso, TXWest Jun 2025target 2029
Wi-Al-199SB
Solar + storage
199 MWIn study El Paso, TXWest Jun 2025target 2028
Battery storage project GEN-2024-178, Harrison County
Battery storage
199 MWIn study Harrison, TXSPP Mar 2025target 2029
Pasture Rose Wind
Onshore wind · Pasture Rose, LLC
199 MWIn study Falls, TXERCOT Mar 2025target 2029
Percy Farm Solar
Solar · Percy Farm Solar 1, LLC
199 MWIn study Matagorda, TXERCOT Mar 2021target 2029
Solar project J2071, Hardin County
Solar
198 MWIn study Hardin, TXMISO Sep 2021target 2028
Barrosos Creek Wind 3
Onshore wind · Cascabel Wind Energy, LLC
198 MWIn study Zapata, TXERCOT Aug 2025target 2028
Barrosos Creek Wind 4
Onshore wind · Cascabel Wind Energy, LLC
198 MWIn study Zapata, TXERCOT Aug 2025target 2028
Wood Fern Wind
Onshore wind · Wood Fern Wind LLC
197 MWIn study Van Zandt, TXERCOT Jan 2025target 2029
Corralitos Wind 3
Onshore wind · Las Crestas Wind Energy, LLC
196 MWIn study Zapata, TXERCOT Jun 2025target 2028
Johnson Grass Solar
Solar · Johnson Grass Solar ,LLC
196 MWIn study Mitchell, TXERCOT Oct 2024target 2028
Corralitos Wind 4
Onshore wind · Las Crestas Wind Energy, LLC
195 MWIn study Zapata, TXERCOT Jun 2025target 2028
Paloma Energy Center
Solar + storage · Harrison Street Development, LLC
194 MWIn study Colorado, TXERCOT Feb 2024target 2027
Steelhead Energy Storage
Battery storage · GRS BESS TEXAS SEVEN, LLC
192 MWIn study Fannin, TXERCOT Feb 2024target 2027
Malachite BESS
Solar + storage · Malachite Storage LLC
191 MWIn study Wharton, TXERCOT May 2024target 2029
Pecos Wind
Wind + storage · Midnight Energy Center, LLC
191 MWIn study Pecos, TXERCOT Jul 2025target 2027
Accalia Point Solar
Solar · Accalia Point Solar LLC
191 MWIn study Cameron, TXERCOT Oct 2020target 2029
Harryoung Solar
Solar + storage · Gransolar Texas Four LLC
190 MWIn study Cameron, TXERCOT Nov 2022target 2028
HarryoungBESS
Solar + storage · Gransolar Texas Four LLC
190 MWIn study Cameron, TXERCOT Oct 2023target 2028
Chacon Creek
Battery storage · Cattlemen BESS LLC
189 MWIn study Medina, TXERCOT Mar 2024target 2027
Blanket Ranch North Solar
Solar + storage · Blanket Ranch North Solar, LLC
189 MWIn study Brown, TXERCOT Jun 2022target 2028
Serrano Storage
Battery storage · Maverick ESS, LLC
186 MWIn study Maverick, TXERCOT Sep 2023target 2026
Wetzel BESS
Battery storage · Brown ESS, LLC
186 MWIn study Brown, TXERCOT Mar 2023target 2026
Montezuma Storage
Battery storage · Montezuma Storage LLC
185 MWIn study Colorado, TXERCOT Sep 2025target 2027
Los Vientos IB Repower
Onshore wind · Los Vientos Windpower IB, LLC
185 MWIn study Willacy, TXERCOT Jul 2024target 2027
Malachite Solar
Solar + storage · Malachite Solar LLC
185 MWIn study Wharton, TXERCOT Feb 2024target 2029
Maldives Solar (Oncor POI)
Solar
184 MWPaused / redesign Scurry, TXERCOT Dec 2022target 2026
Cairos Storage 2
Battery storage · Cairos Solar, LLC
184 MWIn study Kinney, TXERCOT Jul 2024target 2026
Jalisco Peaker
Gas · HEP Power Generation, LLC
184 MWIn study Nueces, TXERCOT Aug 2024target 2029
Basketflower Solar
Solar + storage · Basketflower Solar, LLC
183 MWIn study Eastland, TXERCOT Oct 2024target 2027
Lan Solar SLF
Solar + storage · BR Solar, LLC
182 MWIn study Lamar, TXERCOT May 2020target 2028
Caesar Solar
Solar + storage · Caesar Solar, LLC
182 MWIn study Borden, TXERCOT Jul 2025target 2029
Nanulak BESS
Battery storage · Nanulak BESS, L.L.C.
182 MWIn study Reeves, TXERCOT Mar 2024target 2027
Oak Belt Solar
Solar + storage · Oak Belt Solar, LLC
181 MWIn study Victoria, TXERCOT Dec 2025target 2029
Turkey Creek Solar SLF
Solar + storage · Greenray Solar Corporation
181 MWIn study Kinney, TXERCOT Feb 2024target 2026
Frizzle BESS
Battery storage · Frizzle BESS, L.L.C.
181 MWIn study Ward, TXERCOT Sep 2025target 2027
Hofbrau BESS
Battery storage · Momentum Hofbrau LLC
181 MWIn study Tom Green, TXERCOT Sep 2021target 2028
Amphion Solar Phase 1
Solar · Amphion Solar, LLC
181 MWIn study Atascosa, TXERCOT Oct 2024target 2028
Alliance Solar
Solar
180 MWPaused / redesign Navarro, TXERCOT Jul 2023target 2028
Amberjack2 BESS
Battery storage · Hunt Energy Network, LLC
180 MWIn study Cameron, TXERCOT Jan 2025target 2027
Indigo solar 2
Solar + storage · Indigo Solar 2
180 MWIn study Fisher, TXERCOT Oct 2023target 2027
Whitetail BESS
Battery storage · Hunt Energy Network, LLC
180 MWIn study Mitchell, TXERCOT Feb 2024target 2027
Solar + storage project J2689, Liberty County
Solar + storage
180 MWIn study Liberty, TXMISO Jul 2025target 2026
Solar project GEN-2022-038, Harrison County
Solar
180 MWIn study Harrison, TXSPP Jun 2022target 2029
Battery storage project GEN-2019-065, Smith County
Battery storage
180 MWIn study Smith, TXSPP May 2019target 2026
Bestla Solar
Solar
180 MWPaused / redesign Winkler, TXERCOT Jan 2017
Page 17 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)