United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESQueue requests in study in Texas — page 17
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Monument Hill Solar Solar · RWE Solar Development, LLC |
200 MW | In study |
| Tierra Blanca W Onshore wind · RWE Renewables Development, LLC |
200 MW | Paused / redesign |
| Battery storage project GEN-2024-355, Lubbock County Battery storage |
199 MW | In study |
| Wi-Al2-199SB Solar + storage |
199 MW | In study |
| Wi-Al3-199SB Solar + storage |
199 MW | In study |
| Wi-Al-199SB Solar + storage |
199 MW | In study |
| Battery storage project GEN-2024-178, Harrison County Battery storage |
199 MW | In study |
| Pasture Rose Wind Onshore wind · Pasture Rose, LLC |
199 MW | In study |
| Percy Farm Solar Solar · Percy Farm Solar 1, LLC |
199 MW | In study |
| Solar project J2071, Hardin County Solar |
198 MW | In study |
| Barrosos Creek Wind 3 Onshore wind · Cascabel Wind Energy, LLC |
198 MW | In study |
| Barrosos Creek Wind 4 Onshore wind · Cascabel Wind Energy, LLC |
198 MW | In study |
| Wood Fern Wind Onshore wind · Wood Fern Wind LLC |
197 MW | In study |
| Corralitos Wind 3 Onshore wind · Las Crestas Wind Energy, LLC |
196 MW | In study |
| Johnson Grass Solar Solar · Johnson Grass Solar ,LLC |
196 MW | In study |
| Corralitos Wind 4 Onshore wind · Las Crestas Wind Energy, LLC |
195 MW | In study |
| Paloma Energy Center Solar + storage · Harrison Street Development, LLC |
194 MW | In study |
| Steelhead Energy Storage Battery storage · GRS BESS TEXAS SEVEN, LLC |
192 MW | In study |
| Malachite BESS Solar + storage · Malachite Storage LLC |
191 MW | In study |
| Pecos Wind Wind + storage · Midnight Energy Center, LLC |
191 MW | In study |
| Accalia Point Solar Solar · Accalia Point Solar LLC |
191 MW | In study |
| Harryoung Solar Solar + storage · Gransolar Texas Four LLC |
190 MW | In study |
| HarryoungBESS Solar + storage · Gransolar Texas Four LLC |
190 MW | In study |
| Chacon Creek Battery storage · Cattlemen BESS LLC |
189 MW | In study |
| Blanket Ranch North Solar Solar + storage · Blanket Ranch North Solar, LLC |
189 MW | In study |
| Serrano Storage Battery storage · Maverick ESS, LLC |
186 MW | In study |
| Wetzel BESS Battery storage · Brown ESS, LLC |
186 MW | In study |
| Montezuma Storage Battery storage · Montezuma Storage LLC |
185 MW | In study |
| Los Vientos IB Repower Onshore wind · Los Vientos Windpower IB, LLC |
185 MW | In study |
| Malachite Solar Solar + storage · Malachite Solar LLC |
185 MW | In study |
| Maldives Solar (Oncor POI) Solar |
184 MW | Paused / redesign |
| Cairos Storage 2 Battery storage · Cairos Solar, LLC |
184 MW | In study |
| Jalisco Peaker Gas · HEP Power Generation, LLC |
184 MW | In study |
| Basketflower Solar Solar + storage · Basketflower Solar, LLC |
183 MW | In study |
| Lan Solar SLF Solar + storage · BR Solar, LLC |
182 MW | In study |
| Caesar Solar Solar + storage · Caesar Solar, LLC |
182 MW | In study |
| Nanulak BESS Battery storage · Nanulak BESS, L.L.C. |
182 MW | In study |
| Oak Belt Solar Solar + storage · Oak Belt Solar, LLC |
181 MW | In study |
| Turkey Creek Solar SLF Solar + storage · Greenray Solar Corporation |
181 MW | In study |
| Frizzle BESS Battery storage · Frizzle BESS, L.L.C. |
181 MW | In study |
| Hofbrau BESS Battery storage · Momentum Hofbrau LLC |
181 MW | In study |
| Amphion Solar Phase 1 Solar · Amphion Solar, LLC |
181 MW | In study |
| Alliance Solar Solar |
180 MW | Paused / redesign |
| Amberjack2 BESS Battery storage · Hunt Energy Network, LLC |
180 MW | In study |
| Indigo solar 2 Solar + storage · Indigo Solar 2 |
180 MW | In study |
| Whitetail BESS Battery storage · Hunt Energy Network, LLC |
180 MW | In study |
| Solar + storage project J2689, Liberty County Solar + storage |
180 MW | In study |
| Solar project GEN-2022-038, Harrison County Solar |
180 MW | In study |
| Battery storage project GEN-2019-065, Smith County Battery storage |
180 MW | In study |
| Bestla Solar Solar |
180 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)1,398 · 327.9 GW
- SPP (Southwest Power Pool)61 · 16.6 GW
- MISO (Midcontinent)22 · 6,012 MW
- West (non-ISO utilities)5 · 997 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)