United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 15

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 15 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Harquahala Flats
Solar + storage
900 MWWithdrawn / abandoned Maricopa, AZCAISO May 2017target 2022
Gas project T38, Delaware County
Gas
900 MWWithdrawn / abandoned Delaware, PAPJM Sep 2007target 2012
Cadiz West
Solar
900 MWWithdrawn / abandoned San Bernardino, CACAISO May 2008target 2015
Encina Generating Project (PH. 1 And 2)
Gas
900 MWWithdrawn / abandoned San Diego, CACAISO Aug 2000target 2008
Coal project GEN-2004-018, Choctaw County
Coal
900 MWWithdrawn / abandoned Choctaw, OKSPP Sep 2004target 2010
Gas project IC-030, Blount County
Gas
900 MWWithdrawn / abandoned Blount, ALSoutheast
Gas project G011, Pike County
Gas
900 MWWithdrawn / abandoned Pike, INMISO Oct 1999target 2002
Coal project GEN-2001-007, Platte County
Coal
900 MWWithdrawn / abandoned Platte, MOSPP Feb 2001target 2005
La Posa
Solar
900 MWWithdrawn / abandoned La Paz, AZCAISO May 2008target 2015
Coal project GEN-2006-037, Noble County
Coal
900 MWWithdrawn / abandoned Noble, OKSPP Sep 2006target 2011
Onshore wind project GEN-2010-027, Seward County
Onshore wind
900 MWWithdrawn / abandoned Seward, KSSPP Mar 2010target 2012
Onshore wind project 169, Cochise County
Onshore wind
900 MWWithdrawn / abandoned Cochise, AZWest Jun 2024target 2028
Az Bighorn
Solar
900 MWWithdrawn / abandoned Maricopa, AZCAISO May 2008target 2015
Coal project GEN-2004-013, Atchison County
Coal
900 MWWithdrawn / abandoned Atchison, KSSPP Apr 2004target 2010
Yuha Desert Battery Storage 2
Battery storage
900 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Solar project Q57, Maricopa County
Solar
900 MWWithdrawn / abandoned Maricopa, AZWest Dec 2008target 2013
Solar project Q044a., Yuma County
Solar
900 MWWithdrawn / abandoned Yuma, AZWest May 2008target 2012
Gas project S29, Charles County
Gas
900 MWWithdrawn / abandoned Charles, MDPJM Apr 2007target 2007
Coal project GEN-2004-012, Platte County
Coal
900 MWWithdrawn / abandoned Platte, MOSPP Apr 2004target 2009
Coal project G718, Wapello County
Coal
900 MWWithdrawn / abandoned Wapello, IAMISO Dec 2006target 2009
Ranegras Eagletail
Solar
900 MWWithdrawn / abandoned La Paz, AZCAISO May 2008target 2014
Gas project U2-024, Mcdowell County
Gas
900 MWWithdrawn / abandoned Mcdowell, WVPJM May 2008target 2012
Battery storage project C3-013, Carbon County
Battery storage
900 MWWithdrawn / abandoned Carbon, WYWest Apr 2023target 2029
Gas project GEN-2001-038, Caddo Parish County
Gas
900 MWWithdrawn / abandoned Caddo Parish, LASPP Oct 2001
Combined Cycle
Gas
898 MWWithdrawn / abandoned Plymouth, MAISO-NE Feb 2009target 2015
Gas project LGE-GIS-2013-002, Muhlenberg County
Gas
898 MWWithdrawn / abandoned Muhlenberg, KYSoutheast Oct 2013target 2018
Offshore wind project AG2-348, Sussex County
Offshore wind · US Wind Inc.
898 MWWithdrawn / abandoned Sussex, DEPJM Mar 2021target 2025
Coal project GEN-2009-021, Finney County
Coal
895 MWWithdrawn / abandoned Finney, KSSPP May 2009target 2015
Mattawoman Energy
Gas
894 MWWithdrawn / abandoned Prince George's, MDPJM Oct 2011target 2022
Wonder Solar
Solar + storage
892 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Gas project 28, Utah County
Gas
890 MWWithdrawn / abandoned Utah, UTWest Sep 2003target 2006
Gas project IC-209, Jackson County
Gas
890 MWWithdrawn / abandoned Jackson, GASoutheast Sep 2003
Gas project IC-055, Talladega County
Gas
888 MWWithdrawn / abandoned Talladega, ALSoutheast
Gas project GEN-2016-018, Johnston County
Gas
884 MWWithdrawn / abandoned Johnston, OKSPP Mar 2016target 2021
Vineyard Northeast
Onshore wind · Vineyard Northeast LLC
884 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2024
Offshore wind project AE2-024, Ocean County
Offshore wind
882 MWWithdrawn / abandoned Ocean, NJPJM Dec 2018target 2025
Offshore Wind
Offshore wind
882 MWWithdrawn / abandoned MAISO-NE Feb 2023target 2030
Offshore Wind w/ battery storage
Other
880 MWWithdrawn / abandoned MAISO-NE Apr 2017target 2024
NY Wind Brookhaven
Onshore wind · Bay State Wind LLC
880 MWWithdrawn / abandoned Suffolk, NYNYISO Sep 2018
Atlantic Shores Offshore Wind 9
Offshore wind · Atlantic Shores Offshore Wind Project 2, LLC
880 MWWithdrawn / abandoned Richmond, NYNYISO Jan 2019
Other project 139, Franklin County
Other
880 MWWithdrawn / abandoned Franklin, TNSoutheast Nov 2000
Atlantic Shores Offshore Wind 7
Offshore wind · Atlantic Shores Offshore Wind Project 3, LLC
880 MWWithdrawn / abandoned Nassau, NYNYISO Jan 2019
Gas project LGE-GIS-2011-004, Mercer County
Gas
880 MWWithdrawn / abandoned Mercer, KYSoutheast May 2011target 2018
Atlantic Shores Offshore Wind 8
Offshore wind · Atlantic Shores Offshore Wind Project 3, LLC
880 MWWithdrawn / abandoned Kings, NYNYISO Jan 2019
Three Rocks
Solar + storage
878 MWWithdrawn / abandoned CACAISO Apr 2021target 2024
Limestone 3
Coal · NRG Energy, Inc
875 MWWithdrawn / abandoned ERCOT Aug 2007target 2050
Coal project G872, Bay County
Coal
875 MWWithdrawn / abandoned Bay, MIMISO Oct 2007target 2009
Cotton Energy Center
Gas · FPL Energy, LLC
875 MWWithdrawn / abandoned ERCOT Dec 2007target 2050
Other project G210 CONS 103, Saginaw County
Other
875 MWWithdrawn / abandoned Saginaw, MIMISO Jun 2001target 2000
Cosmos
Battery storage
874 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Page 15 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)