BATTERY STORAGE Β· WEST

Battery storage project C3-013, Carbon County

Battery storage project C3-013, Carbon County is a 900 MW battery storage request withdrawn in the West interconnection queue, in Carbon County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C3-013
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Aeolus substation
Location
Carbon County, Wyoming
Technology
Other Storage: 900 MW
Total requested
900 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
24 April 2023
Proposed online date
May 2029

Location

Marker shows the centre of Carbon County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Carbon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem