Completed queue projects in the USA — page 15

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4,787563.7 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4,787 requests · page 15 of 96
ProjectCapacityStatusLocationRegionQueuedOnline
Rattlesnake W 1
Onshore wind · Invenergy
211 MWOperating ERCOT Dec 20092015
Mesquite Creek W
Onshore wind · Sumitomo
211 MWOperating ERCOT Jun 20072015
Stillhouse Solar
Solar · Stillhouse Solar LLC
211 MWOperating Bell, TXERCOT Nov 20212025
Onshore wind project 122, Columbia County
Onshore wind · PacifiCorp Commercial & Trading
211 MWOperating Columbia, WAWest Feb 2007target 2008
Gas project G064, Hamilton County
Gas
210 MWOperating Hamilton, INMISO Oct 20002005
Onshore wind project 1, Walla Walla County
Onshore wind · FPL Energy Vansycle, LLC
210 MWOperating Walla Walla, WAWest Sep 2000target 2001
Gas project G361, Isanti County
Gas
210 MWOperating Isanti, MNMISO Jul 20022006
Gas project 270, Elmore County
Gas
210 MWOperating Elmore, IDWest Oct 2008
California Valley PV
Solar
210 MWOperating San Luis Obispo, CACAISO Jan 20072014
Canadian Breaks Wind
Onshore wind · Macquarie Cap
210 MWOperating Oldham, TXERCOT Jul 20102019
West Deptford Energy Station
Gas
210 MWOperating Gloucester, NJPJM Nov 20102015
Onshore wind project J535, Sac County
Onshore wind
210 MWOperating Sac, IAMISO Nov 20152020
Reloj Del Sol Wind
Onshore wind · EDP Renewables
209 MWOperating Zapata, TXERCOT Mar 20152022
Holy ESS
Other · Citadel BESS LLC
209 MWOperating Harris, TXERCOT Nov 20212024
Roscoe 1
Onshore wind · Airtricity
209 MWOperating ERCOT Mar 2006target 2008
Gas project 366, Broward County
Gas · FPL
209 MWOperating Broward, FLSoutheast Feb 20192022
Vera Wind
Onshore wind · Longroad Energy
209 MWOperating Knox, TXERCOT Apr 20172021
Desert Wind Farm
Onshore wind
208 MWOperating Pasquotank, NCPJM Feb 20102017
Medway Peaker - SEMARI
Gas
208 MWOperating Norfolk, MAISO-NE May 2014target 2019
Karankawa Wind
Onshore wind · Avangrid
207 MWOperating San Patricio, TXERCOT Oct 20152019
Callisto I Energy Center
Other · Callisto I energy center LLC
206 MWOperating Harris, TXERCOT Mar 20212024
Libra BESS
Other · Libra Storage LLC
206 MWOperating Guadalupe, TXERCOT Jun 20202024
Tranquillity 8
Solar
206 MWOperating Fresno, CACAISO Apr 20142018
Mercury Solar
Solar + storage · Mercury Solar, LLC
206 MWOperating Hill, TXERCOT Feb 20192023
Mercury II Solar
Solar + storage · Mercury II Solar, LLC
206 MWOperating Hill, TXERCOT Jan 20212023
Redfish Wind Project
Onshore wind · Eon
206 MWOperating ERCOT Sep 20082012
Peach Bottom Units 2 & 3
Nuclear
206 MWOperating York, PAPJM Dec 20092016
McLean (Shakes) Solar
Solar · Cypress Creek Renewables
206 MWOperating Zavala, TXERCOT May 20172023
Cachi BESS
Battery storage · BRP Cachi BESS LLC
206 MWOperating Guadalupe, TXERCOT Aug 20202025
Walstrom BESS
Battery storage · Sealy Power LLC
205 MWOperating ERCOT Jul 20212025
Pennsylvania Chemicals Generating Facility
Gas
205 MWOperating Beaver, PAPJM Apr 20132021
Gas project GEN-2011-045, Lubbock County
Gas
205 MWOperating Lubbock, TXSPP Sep 20112013
Gas project GEN-2010-006, Lubbock County
Gas
205 MWOperating Lubbock, TXSPP Mar 20102011
Gas project G370, Minnehaha County
Gas
205 MWOperating Minnehaha, SDMISO Oct 20032007
Anemoi Energy Storage
Other · Anemoi Energy Storage, LLC
205 MWOperating Hidalgo, TXERCOT Sep 20212024
Corazon Storage
Solar + storage · Guajillo Energy Storage LLC
205 MWOperating Webb, TXERCOT Aug 20212025
Holstein Solar
Solar · Holstein Solar
205 MWOperating Nolan, TXERCOT Jul 20162020
Tidwell Prairie Storage 1
Battery storage · Tidwell Prairie LLC
204 MWOperating Robertson, TXERCOT Jul 20202025
Taygete II Solar
Solar · West Texas Solar Project II LLC
204 MWOperating Pecos, TXERCOT Dec 20182023
Horizon Solar
Solar · Horizon Solar, LLC
204 MWOperating Frio, TXERCOT Mar 20192024
Ebony Energy Storage
Other · Ebony Energy Storage, LLC
204 MWOperating Comal, TXERCOT Feb 20212024
SunRay
Solar · AP Sunray LLC
204 MWOperating Uvalde, TXERCOT Jul 20192024
Westoria Solar
Solar · Brazoria West Solar Project, LLC
203 MWOperating Brazoria, TXERCOT Jun 20182022
Danciger Solar
Solar · Brazoria County Solar Project, LLC
203 MWOperating Brazoria, TXERCOT Jun 20182023
Gas project GEN-2012-037, Hale County
Gas
203 MWOperating Hale, TXSPP Sep 20122015
Crossett Power Batt
Other · Crossett Power Management LLC
203 MWOperating Crane, TXERCOT Jun 20202022
Gas project GEN-2013-016, Hale County
Gas
203 MWOperating Hale, TXSPP Mar 20132019
Aureola Solar
Solar · Ben Milam Solar 1
203 MWOperating Milam, TXERCOT Dec 20192024
Rowland Solar II
Solar · Cutlass Solar II LLC
203 MWOperating Fort Bend, TXERCOT Dec 20202024
Corazon Solar
Solar · Corazon Energy, LLC
203 MWOperating Webb, TXERCOT Sep 20132021
Page 15 of 96

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)