ONSHORE WIND Β· ERCOT

Roscoe 1

Roscoe 1 is a 209 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Mar 2006 (completed)
  2. ConsentedOct 2006 (completed)
  3. Construction (completed)
  4. OperatingTarget Jan 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
07INR0045e
Grid region
ERCOT (Texas)
Developer
Airtricity
Connection point (POI)
TKWSW_ROSCOE34.500
Technology
Wind: 209 MW
Total requested
209 MW
Study phase
IA
Queue status
Operational
Entered queue
31 March 2006
Agreement signed
19 October 2006
Proposed online date
January 2008

Location

No county location in the queue data.