United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTMercury Solar
Mercury Solar is a 206 MW solar + storage request built and operating in the ERCOT interconnection queue, in Hill County, Texas.
Request details
- Queue ID
- 21INR0257
- Grid region
- ERCOT (Texas)
- Developer
- Mercury Solar, LLC
- Connection point (POI)
- 68092 Liberty Station 345kV
- Location
- Hill County, Texas
- Technology
- Solar: 206 MW · Battery
- Total requested
- 206 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 13 February 2019
- Agreement signed
- 18 October 2021
- Proposed online date
- June 2025
- Came online
- October 2023
Location
Marker shows the centre of Hill County; the queue data does not give exact sites.
Other requests in Hill County
- Compadre SolarSolar · 406 MW · agreement signed
- Blue Skies BESSBattery storage · 306 MW · agreement signed
- Aquilla Lake 3 WindOnshore wind · 297 MW · agreement signed
- OCI Cobb Creek SolarSolar + storage · 203 MW · agreement signed
- OCI Cobb Creek ESSSolar + storage · 202 MW · agreement signed
- Padrino SolarSolar · 201 MW · agreement signed
- High Noon SolarSolar + storage · 182 MW · agreement signed
- Vial BESSBattery storage · 135 MW · agreement signed
- Three W SolarSolar · 111 MW · agreement signed
- Midpoint SolarSolar · 98.3 MW · agreement signed
- High Noon StorageSolar + storage · 94.0 MW · agreement signed
- Payne BattlecreekSolar · 85.0 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem