πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Holstein Solar

Holstein Solar is a 205 MW solar request built and operating in the ERCOT interconnection queue, in Nolan County, Texas.

Queue statusOperating
  1. PlanningQueued Jul 2016 (completed)
  2. ConsentedSep 2018 (completed)
  3. Construction (completed)
  4. OperatingJan 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
19INR0009
Grid region
ERCOT (Texas)
Developer
Holstein Solar
Connection point (POI)
11406 Central Bluff 345kV
Location
Nolan County, Texas
Technology
Solar: 205 MW
Total requested
205 MW
Study phase
IA
Queue status
Operational
Entered queue
25 July 2016
Agreement signed
15 September 2018
Proposed online date
June 2020
Came online
January 2020

Location

Marker shows the centre of Nolan County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Nolan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem