United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Redfish Wind Project

Redfish Wind Project is a 206 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Sep 2008 (completed)
  2. ConsentedFeb 2011 (completed)
  3. Construction (completed)
  4. OperatingSep 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
10INR0060
Grid region
ERCOT (Texas)
Developer
Eon
Technology
Wind: 206 MW
Total requested
206 MW
Study phase
IA
Queue status
Operational
Entered queue
10 September 2008
Agreement signed
25 February 2011
Proposed online date
September 2012
Came online
September 2012

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem