Withdrawn queue requests in the USA — page 148

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 148 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2006-4, Logan County
Onshore wind
200 MWWithdrawn / abandoned Logan, COWest Dec 2006target 2008
Solar project J1093, Desha County
Solar
200 MWWithdrawn / abandoned Desha, ARMISO Mar 2018target 2021
Battery storage project GEN-2018-036, Scotts Bluff County
Battery storage
200 MWWithdrawn / abandoned Scotts Bluff, NESPP May 20182023
Solar project J1322, Eaton County
Solar
200 MWWithdrawn / abandoned Eaton, MIMISO Apr 2019target 2022
Solar project J1533, Adams County
Solar
200 MWWithdrawn / abandoned Adams, IAMISO Jun 2020target 2024
Onshore wind project Company EY, Lassen County
Onshore wind
200 MWWithdrawn / abandoned Lassen, CAWest Apr 2010target 2016
Onshore wind project G824, Mower County
Onshore wind
200 MWWithdrawn / abandoned Mower, MNMISO Jul 2007target 2010
Chiltepin Solar
Solar · Chiltepin Solar-Storage, LLC
200 MWWithdrawn / abandoned ERCOT Apr 2021target 2025
Solar project J1940, Monroe County
Solar
200 MWWithdrawn / abandoned Monroe, MIMISO Aug 2021target 2023
Onshore wind project GI-29, Osage County
Onshore wind
200 MWWithdrawn / abandoned Osage, OKSoutheast May 2008target 2011
Battery storage project 61, Kitsap County
Battery storage
200 MWWithdrawn / abandoned Kitsap, WAWest Aug 2018target 2022
Battery storage project LGE-GIS-2021-024, Floyd County
Battery storage
200 MWWithdrawn / abandoned Floyd, INSoutheast Oct 2021target 2024
Southern Tier Energy Center
Battery storage · Southern Tier Energy Center, LLC
200 MWWithdrawn / abandoned Tioga, NYNYISO Aug 2022
Cottonwood Bayou Solar II
Solar · Cottonwood Bayou Solar, LLC
200 MWWithdrawn / abandoned Brazoria, TXERCOT Dec 2018target 2024
Onshore wind project J3533, Randolph County
Onshore wind
200 MWWithdrawn / abandoned Randolph, MOMISO Apr 2024target 2028
Solar project 360, Simpson County
Solar
200 MWWithdrawn / abandoned Simpson, KYSoutheast Mar 2019
Onshore wind project GEN-2018-123, Ellsworth County
Onshore wind
200 MWWithdrawn / abandoned Ellsworth, KSSPP Nov 20182025
Solar project AH1-465, Greensville County
Solar
200 MWWithdrawn / abandoned Greensville, VAPJM Sep 2021target 2024
Onshore wind project GI-0202, Codington County
Onshore wind
200 MWWithdrawn / abandoned Codington, SDWest Feb 2002
Solar project 359, Logan County
Solar
200 MWWithdrawn / abandoned Logan, KYSoutheast Mar 2019
Onshore wind project GI-1104, Pennington County
Onshore wind
200 MWWithdrawn / abandoned Pennington, SDWest Sep 2011target 2010
Battery storage project J2357, Lafourche Parish County
Battery storage
200 MWWithdrawn / abandoned Lafourche Parish, LAMISO Sep 2022target 2027
Gas project 229, Clay County
Gas
200 MWWithdrawn / abandoned Clay, MSSoutheast Oct 2011
Battery Storage
Battery storage
200 MWWithdrawn / abandoned Middlesex, MAISO-NE Oct 2020target 2023
Solar project J1428, Cass County
Solar
200 MWWithdrawn / abandoned Cass, NDMISO Apr 2019target 2022
Solar project Q235, Maricopa County
Solar
200 MWWithdrawn / abandoned Maricopa, AZWest Mar 2016target 2021
Solar + storage project Q383, Yuma County
Solar + storage
200 MWWithdrawn / abandoned Yuma, AZWest Mar 2021target 2025
Tuxedo I
Onshore wind · Arranz Wind Tuxedo I,LLC
200 MWWithdrawn / abandoned ERCOT Aug 2010target 2013
Onshore wind project G864, White County
Onshore wind
200 MWWithdrawn / abandoned White, INMISO Sep 2007target 2013
Solar project GEN-2022-243, Foard County
Solar
200 MWWithdrawn / abandoned Foard, TXSPP Mar 2023target 2027
Solar project J2083, Allen Parish County
Solar
200 MWWithdrawn / abandoned Allen Parish, LAMISO Dec 2021target 2024
Brangus Storage
Other · 245CK 8me LLC
200 MWWithdrawn / abandoned Kinney, TXERCOT Jan 2020target 2023
Solar + storage project IC-901, Glynn County
Solar + storage
200 MWWithdrawn / abandoned Glynn, GASoutheast Aug 2020target 2023
CPV Steele Hill WindFarm
Onshore wind · CPV Renewable Energy LLC
200 MWWithdrawn / abandoned ERCOT Mar 2008
Onshore wind project 330, Juab County
Onshore wind
200 MWWithdrawn / abandoned Juab, UTWest Apr 2010target 2014
Onshore wind project 13, Garfield County
Onshore wind
200 MWWithdrawn / abandoned Garfield, WAWest Jan 2008target 2009
Solar project 439, Mcminn County
Solar
200 MWWithdrawn / abandoned Mcminn, TNSoutheast Jun 2020
Solar project GEN-2018-103, Jackson County
Solar
200 MWWithdrawn / abandoned Jackson, MOSPP Nov 2018target 2023
Solar project J1923, Huron County
Solar
200 MWWithdrawn / abandoned Huron, MIMISO Aug 2021target 2023
Battery storage project Q73, Los Angeles County
Battery storage
200 MWWithdrawn / abandoned Los Angeles, CAWest Jul 2019target 2023
Onshore wind project AD2-087, Darke County
Onshore wind
200 MWWithdrawn / abandoned Darke, OHPJM Mar 2018target 2020
Onshore wind project AE2-153, Kankakee County
Onshore wind
200 MWWithdrawn / abandoned Kankakee, ILPJM Mar 2019target 2021
Solar + storage project 375, Deer Lodge County
Solar + storage
200 MWWithdrawn / abandoned Deer Lodge, MTWest Mar 2020target 2023
Mustang Draw Solar
Solar · Lincoln Clean
200 MWWithdrawn / abandoned ERCOT Mar 2015target 2016
Onshore wind project GEN-2008-049, Cloud County
Onshore wind
200 MWWithdrawn / abandoned Cloud, KSSPP May 2008target 2012
Solar project J1384, Evangeline Parish County
Solar
200 MWWithdrawn / abandoned Evangeline Parish, LAMISO Apr 2019target 2022
Battery storage project 147, Skagit County
Battery storage
200 MWWithdrawn / abandoned Skagit, WAWest Apr 2024target 2027
Solar project AG1-005, Stephenson County
Solar · Sky Yield Solar Farm, LLC
200 MWWithdrawn / abandoned Stephenson, ILPJM Apr 2020target 2023
Solar project GEN-2021-008, Mckenzie County
Solar
200 MWWithdrawn / abandoned Mckenzie, NDSPP May 2021target 2030
Onshore wind project J1966, Clinton County
Onshore wind
200 MWWithdrawn / abandoned Clinton, INMISO Mar 2022target 2025
Page 148 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)