United States βΊ Grid βΊ Interconnection queues βΊ Indiana
BATTERY STORAGE Β· SOUTHEASTBattery storage project LGE-GIS-2021-024, Floyd County
Battery storage project LGE-GIS-2021-024, Floyd County is a 200 MW battery storage request withdrawn in the Southeast interconnection queue, in Floyd County, Indiana, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2021 (completed)
- Withdrawn / abandonedFeb 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- LGE-GIS-2021-024
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Primary: Paddys West 345 kV ; Alternate: Paddys West-Cane Run Tap 345 kV
- Location
- Floyd County, Indiana
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 5 October 2021
- Proposed online date
- September 2024
- Withdrawn
- February 2023
Location
Marker shows the centre of Floyd County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem