United States βΊ Grid βΊ Interconnection queues βΊ Michigan
SOLAR Β· MISOSolar project J1923, Huron County
Solar project J1923, Huron County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Huron County, Michigan, connecting to ITC.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedDec 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1923
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC
- Connection point (POI)
- Rapson 120 kV substation
- Location
- Huron County, Michigan
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 3; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 19 August 2021
- Proposed online date
- November 2023
- Withdrawn
- December 2021
Location
Marker shows the centre of Huron County; the queue data does not give exact sites.
Other requests in Huron County
- Solar project J1525, Huron CountySolar Β· 200 MW Β· agreement signed
- Battery storage project J466, Huron CountyBattery storage Β· 30.0 MW Β· agreement signed
- Battery storage project J2590, Huron CountyBattery storage Β· 500 MW Β· in study
- Onshore wind project J3966, Huron CountyOnshore wind Β· 480 MW Β· in study
- Onshore wind project J4203, Huron CountyOnshore wind Β· 350 MW Β· in study
- Battery storage project J4095, Huron CountyBattery storage Β· 300 MW Β· in study
- Battery storage project J4094, Huron CountyBattery storage Β· 300 MW Β· in study
- Onshore wind project J3971, Huron CountyOnshore wind Β· 255 MW Β· in study
- Battery storage project J2628, Huron CountyBattery storage Β· 250 MW Β· in study
- Battery storage project J4058, Huron CountyBattery storage Β· 250 MW Β· in study
- Solar project J2676, Huron CountySolar Β· 200 MW Β· in study
- Onshore wind project J3967, Huron CountyOnshore wind Β· 170 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem