Solar + storage project 375, Deer Lodge County

Solar + storage project 375, Deer Lodge County is a 200 MW solar + storage request withdrawn in the West interconnection queue, in Deer Lodge County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
375
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
230kV at Anaconda Mill Creek Substation
Location
Deer Lodge County, Montana
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
19 March 2020
Proposed online date
February 2023

Location

Marker shows the centre of Deer Lodge County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Deer Lodge County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem