United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA — page 127

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 127 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Amelia Energy Facility
Solar · Amelia Energy Facility, LLC
20.0 MWIn study Amelia, VAPJM May 2020target 2023
Solar + storage project T2-039, Emery County
Solar + storage
20.0 MWIn study Emery, UTWest Sep 2025target 2026
Reid Energy Center
Battery storage · Reid Energy Center, LLC
20.0 MWIn study Prince William, VAPJM Feb 2025target 2022
Flat Hill Solar
Solar · Flat Hill Solar NY LLC.
20.0 MWIn study Herkimer, NYNYISO May 2019
Solar project G1069, Harney County
Solar
20.0 MWIn study Harney, ORWest Jul 2024target 2025
Solar project J3065, Oceana County
Solar
20.0 MWIn study Oceana, MIMISO Sep 2022target 2025
Coal project GI-39, New Madrid County
Coal
20.0 MWIn study New Madrid, MOSoutheast Oct 2009target 2011
Dog Corners Solar
Solar · SunEast Dog Corners Solar LLC
20.0 MWIn study Cayuga, NYNYISO Nov 2016target 2026
Solar project AH2-160, Highland County
Solar
20.0 MWIn study Highland, OHPJM Mar 2022target 2025
Evergreen Energy Center
Battery storage · Evergreen Energy Center, LLC
20.0 MWIn study Loudoun, VAPJM Feb 2025target 2022
Solar + storage project T2-044, Millard County
Solar + storage
20.0 MWIn study Millard, UTWest Sep 2025target 2027
Switchgrass Solar 1
Solar
20.0 MWPaused / redesign Accomack, VAPJM Feb 2020target 2025
Battery storage project AI2-010, Hanover County
Battery storage
20.0 MWIn study Hanover, VAPJM Nov 2022target 2025
Solar + storage project T2-045, Millard County
Solar + storage
20.0 MWIn study Millard, UTWest Sep 2025target 2027
Kce NY 10
Battery storage · KCE NY 10, LLC
20.0 MWIn study Erie, NYNYISO Mar 2019target 2026
Solar project AH2-063, Beaver County
Solar
20.0 MWIn study Beaver, PAPJM Dec 2021target 2023
Battery storage project G0830, Thurston County
Battery storage
20.0 MWIn study Thurston, WAWest Dec 2022target 2026
Solar + storage project AI2-435, Berks County
Solar + storage
20.0 MWIn study Berks, PAPJM Mar 2023target 2026
Morris Solar
Solar · Morris Solar NY LLC
20.0 MWIn study St. Lawrence, NYNYISO Jan 2021target 2028
Solar + storage project T2-050, Lake County
Solar + storage
20.0 MWIn study Lake, ORWest Sep 2025target 2027
Gas project 199, Anderson County
Gas
20.0 MWIn study Anderson, SCSoutheast Jun 2023
Solar + storage project T2-043, Millard County
Solar + storage
20.0 MWIn study Millard, UTWest Sep 2025target 2027
Cedar Creek Solar
Solar
20.0 MWPaused / redesign Kent, DEPJM Apr 2017target 2027
HU-Pauls
Solar
20.0 MWPaused / redesign Huntingdon, PAPJM Mar 2019target 2027
Solar + storage project AI2-442, Luzerne County
Solar + storage
20.0 MWIn study Luzerne, PAPJM Mar 2023target 2027
Gas project AH2-111, Monroe County
Gas
20.0 MWIn study Monroe, OHPJM Feb 2022target 2022
Montour 1
Solar
20.0 MWPaused / redesign Columbia, PAPJM Mar 2019target 2025
Solar project AG2-193, Henrico County
Solar · Virginia Electric and Power Company
20.0 MWIn study Henrico, VAPJM Feb 2025target 2023
Clear View Solar
Solar · Clear View LLC
20.0 MWIn study Steuben, NYNYISO Apr 2020
Solar project G0516, Sherman County
Solar
20.0 MWIn study Sherman, ORWest Oct 2015target 2016
Blue Creek Wind Farm
Solar
20.0 MWPaused / redesign Van Wert, OHPJM Feb 2017target 2024
Battery storage project AH2-050, Accomack County
Battery storage
20.0 MWIn study Accomack, VAPJM Dec 2021target 2025
Sparkl BESS
Battery storage
20.0 MWPaused / redesign Guadalupe, TXERCOT Dec 2019
Solar + storage project AH2-410
Solar + storage
20.0 MWIn study KYPJM Mar 2022target 2025
Battery storage project G0942, Thurston County
Battery storage
20.0 MWIn study Thurston, WAWest Sep 2023target 2026
Solar project AI2-346, Harrison County
Solar
20.0 MWIn study Harrison, OHPJM Mar 2023target 2025
Solar + storage project AI2-439, Centre County
Solar + storage
20.0 MWIn study Centre, PAPJM Mar 2023target 2027
Ticonderoga Solar
Solar · ELP Ticonderoga Solar LLC
20.0 MWIn study Essex, NYNYISO Jun 2018target 2026
Solar + storage project AI1-216, Centre County
Solar + storage
20.0 MWIn study Centre, PAPJM Sep 2022target 2024
Battery storage project GEN-2024-SR12, Lamoure County
Battery storage
20.0 MWIn study Lamoure, NDSPP May 2024target 2026
Solar + storage project 25N-SG6, Lyon County
Solar + storage
20.0 MWIn study Lyon, NVWest Oct 2025target 2029
Solar project AG2-356, Bradford County
Solar · Robin Solar LLC
20.0 MWIn study Bradford, PAPJM Jan 2025target 2023
Battery storage project C2-209, Uintah County
Battery storage · Revolve Vernal BESS, LLC
20.0 MWPaused / redesign Uintah, UTWest May 2022target 2026
Battery storage project 120, Polk County
Battery storage
20.0 MWIn study Polk, FLSoutheast May 2025target 2027
Solar project AH1-072, Dickenson County
Solar · Bold Camp CF Solar, LLC
20.0 MWIn study Dickenson, VAPJM Mar 2025target 2024
Solar project G0524, Wasco County
Solar
20.0 MWIn study Wasco, ORWest Jan 2016target 2018
Geothermal project Company RB, Lander County
Geothermal
20.0 MWIn study Lander, NVWest Oct 2024target 2029
Basalt Solar
Solar
20.0 MWPaused / redesign Uvalde, TXERCOT Jul 2017
Geothermal project T2-004, Sevier County
Geothermal
20.0 MWIn study Sevier, UTWest Aug 2025
Fairway Solar
Solar · Fairway Solar NY LLC
20.0 MWIn study St. Lawrence, NYNYISO May 2019target 2028
Page 127 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)