United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Solar project AH1-072, Dickenson County

Solar project AH1-072, Dickenson County is a 20.0 MW solar request in interconnection study in the PJM interconnection queue, in Dickenson County, Virginia, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH1-072
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Bold Camp CF Solar, LLC
Connection point (POI)
Red Onion - VC5 69 kV
Location
Dickenson County, Virginia
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
3 March 2025
Proposed online date
March 2024

Location

Marker shows the centre of Dickenson County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Dickenson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem