OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 111

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 111 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Hallows
Battery storage
230 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Solar project AH1-624, Clearfield County
Solar
230 MWWithdrawn / abandoned Clearfield, PAPJM Sep 2021target 2025
Sagebrush 6 Hybrid
Solar + storage
230 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Gas project G033, Monroe County
Gas
230 MWWithdrawn / abandoned Monroe, IAMISO Mar 2000target 2001
Onshore wind project 375, Carbon County
Onshore wind
230 MWWithdrawn / abandoned Carbon, WYWest Mar 2011target 2014
Cumberland
Gas
230 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2016target 2023
Erie Canal BESS
Battery storage · RWE Solar Development
230 MWWithdrawn / abandoned Niagara, NYNYISO Jul 2023
Astoria Uprate
Gas · Astoria Energy, LLC
230 MWWithdrawn / abandoned Queens, NYNYISO Apr 2007
Solar project J3271, Mississippi County
Solar
230 MWWithdrawn / abandoned Mississippi, ARMISO Apr 2024target 2028
Sinton Wind
Onshore wind · Gamesa Energia Southwest
230 MWWithdrawn / abandoned ERCOT Jun 2004target 2050
Solar + storage project GEN-2023-028, Mayes County
Solar + storage
230 MWWithdrawn / abandoned Mayes, OKSPP Oct 2023target 2028
Onshore wind project GEN-2010-033, Hale County
Onshore wind
230 MWWithdrawn / abandoned Hale, TXSPP Jun 2010target 2014
Solar project GI-2018-19, Pueblo County
Solar
230 MWWithdrawn / abandoned Pueblo, COWest Mar 2018target 2020
Solar + storage project 111, Greenlee County
Solar + storage
230 MWWithdrawn / abandoned Greenlee, AZWest Jan 2022target 2024
Onshore wind project GEN-2013-021, Keith County
Onshore wind
230 MWWithdrawn / abandoned Keith, NESPP Jul 2013target 2016
Allium
Solar + storage
229 MWWithdrawn / abandoned San Benito, CACAISO Apr 2020target 2023
SPC Nacogdoches
Gas · Southern Power Company
229 MWWithdrawn / abandoned ERCOT Aug 2013target 2018
Other project 49, Hamilton County
Other
229 MWWithdrawn / abandoned Hamilton, TNSoutheast Jun 1999
Solar project GEN-2017-055, Lancaster County
Solar
228 MWWithdrawn / abandoned Lancaster, NESPP May 20172023
Solar project J2709, Miami County
Solar
228 MWWithdrawn / abandoned Miami, INMISO Sep 2022target 2027
Shavers Valley Wind Farm
Onshore wind
228 MWWithdrawn / abandoned Riverside, CACAISO Jul 2007target 2010
Mercedes II BESS
Battery storage · SMT Mercedes II, LLC
228 MWWithdrawn / abandoned Hidalgo, TXERCOT May 2023target 2025
PowerVault BESS
Other · SMT Dallas V, LLC
228 MWWithdrawn / abandoned Dallas, TXERCOT Jul 2023target 2025
Onshore wind project GEN-2016-096, Fillmore County
Onshore wind
228 MWWithdrawn / abandoned Fillmore, NESPP Nov 20162020
Allegro Hybrid Solar
Solar + storage
227 MWWithdrawn / abandoned Kern, CACAISO Apr 2020target 2023
Mule Car
Battery storage
227 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Gas project GEN-2014-016, Nacogdoches County
Gas
227 MWWithdrawn / abandoned Nacogdoches, TXSPP Jun 2014target 2018
Solar project 371, Lake County
Solar
227 MWWithdrawn / abandoned Lake, TNSoutheast May 2019
Solar project 370, Colbert County
Solar
227 MWWithdrawn / abandoned Colbert, ALSoutheast May 2019
Onshore wind project GEN-2017-143, Wagoner County
Onshore wind
227 MWWithdrawn / abandoned Wagoner, OKSPP Nov 2017target 2020
Solar project 369, Lawrence County
Solar
227 MWWithdrawn / abandoned Lawrence, TNSoutheast May 2019
Lacuna Energy Storage
Battery storage
227 MWWithdrawn / abandoned Alameda, CACAISO Apr 2021target 2024
Flyway Solar
Solar + storage
227 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2024
Combustion Turbine
Gas
227 MWWithdrawn / abandoned Providence, RIISO-NE Feb 2015target 2019
Onshore wind project J2363, Washington County
Onshore wind
226 MWWithdrawn / abandoned Washington, IAMISO Sep 2022target 2030
Gas project 53, Pima County
Gas
226 MWWithdrawn / abandoned Pima, AZWest Nov 2016target 2018
Battery Storage
Battery storage
226 MWWithdrawn / abandoned Merrimack, NHISO-NE Mar 2023target 2027
Onshore wind project GEN-2023-141, Osborne County
Onshore wind
225 MWWithdrawn / abandoned Osborne, KSSPP Oct 2023target 2028
Solar + storage project AE2-307, Will County
Solar + storage
225 MWWithdrawn / abandoned Will, ILPJM Mar 2019target 2021
Gas project X2-019, Lake County
Gas
225 MWWithdrawn / abandoned Lake, ILPJM May 2011target 2015
Battery storage project AH1-762, Will County
Battery storage · Crete Bess, LLC
225 MWWithdrawn / abandoned Will, ILPJM target 2028
Solar project GEN-2024-387
Solar
225 MWWithdrawn / abandoned SPP Mar 2025target 2031
Onshore wind project GEN-2022-096, Osborne County
Onshore wind
225 MWWithdrawn / abandoned Osborne, KSSPP Nov 2022target 2028
Solar + storage project G0845, Grant County
Solar + storage
225 MWWithdrawn / abandoned Grant, WAWest Feb 2023target 2026
Solar project GEN-2023-194, Cherokee County
Solar
225 MWWithdrawn / abandoned Cherokee, KSSPP Oct 2023target 2028
Solar project GI-94, Jasper County
Solar
225 MWWithdrawn / abandoned Jasper, MOSoutheast Dec 2020target 2023
Coyote Run Windfarm
Onshore wind · FPL Energy, LLC
225 MWWithdrawn / abandoned ERCOT Mar 2006target 2050
Battery storage project GEN-2022-182, Tillman County
Battery storage
225 MWWithdrawn / abandoned Tillman, OKSPP Feb 2023target 2026
Solar project AG1-528
Solar
225 MWWithdrawn / abandoned WVPJM Sep 2020target 2023
Gas project S17, Charles County
Gas
225 MWWithdrawn / abandoned Charles, MDPJM Mar 2007target 2017
Page 111 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)