OTHER Β· ERCOT

PowerVault BESS

PowerVault BESS is a 228 MW other request withdrawn in the ERCOT interconnection queue, in Dallas County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2023 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0453
Grid region
ERCOT (Texas)
Developer
SMT Dallas V, LLC
Connection point (POI)
Tap 138 kV 3035 LVBRD2 - 3032 LVBRD2T_x000D_
Location
Dallas County, Texas
Technology
Other: 228 MW
Total requested
228 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
17 July 2023
Proposed online date
June 2025
Withdrawn
October 2023

Location

Marker shows the centre of Dallas County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Dallas County