Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 104 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-0822, Pondera County
Onshore wind
250 MWWithdrawn / abandoned Pondera, MTWest Oct 2008target 2010
Solar + storage project G0652, Umatilla County
Solar + storage
250 MWWithdrawn / abandoned Umatilla, ORWest Jul 2020target 2025
Battery storage project Q05, Maricopa County
Battery storage
250 MWWithdrawn / abandoned Maricopa, AZWest Jun 2023target 2027
Ward Valley Solar Energy 2
Solar
250 MWWithdrawn / abandoned San Bernardino, CACAISO May 2008target 2015
Onshore wind project MPC02200, Barnes County
Onshore wind
250 MWWithdrawn / abandoned Barnes, NDMISO Jun 2009target 2010
Solar + storage project 1224, San Juan County
Solar + storage
250 MWWithdrawn / abandoned San Juan, UTWest Apr 2020target 2023
Solar project GEN-2024-146, Craig County
Solar
250 MWWithdrawn / abandoned Craig, OKSPP Mar 2025target 2031
Wind Project-Phase 2( MPS Queue # 2&3)
Onshore wind
250 MWWithdrawn / abandoned ISO-NE Aug 2006target 2012
Solar project Q41, Yuma County
Solar
250 MWWithdrawn / abandoned Yuma, AZWest Jan 2008target 2012
Solar project GEN-2023-122, Coffey County
Solar
250 MWWithdrawn / abandoned Coffey, KSSPP Oct 2023target 2030
Solar project J1412, Porter County
Solar
250 MWWithdrawn / abandoned Porter, INMISO Apr 2019target 2023
Onshore wind project J2367, Lamoure County
Onshore wind
250 MWWithdrawn / abandoned Lamoure, NDMISO Sep 2022target 2030
Battery storage project GEN-2022-141, Lubbock County
Battery storage
250 MWWithdrawn / abandoned Lubbock, TXSPP Feb 2023target 2027
Battery storage project Q03, Maricopa County
Battery storage
250 MWWithdrawn / abandoned Maricopa, AZWest Feb 2023target 2027
Solar + storage project 5, Sacramento County
Solar + storage
250 MWWithdrawn / abandoned Sacramento, CAWest Nov 2020target 2029
Solar + storage project IA-PNM-2023-21, San Juan County
Solar + storage
250 MWWithdrawn / abandoned San Juan, NMWest Sep 2023target 2028
Onshore wind project 239, Fremont County
Onshore wind
250 MWWithdrawn / abandoned Fremont, WYWest Aug 2008target 2012
Solar project J2441, Beauregard Parish County
Solar
250 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2026
Onshore wind project GEN-2015-092, Grady County
Onshore wind
250 MWWithdrawn / abandoned Grady, OKSPP Sep 20152020
Grandview 6 W
Onshore wind · Eon
250 MWWithdrawn / abandoned ERCOT Jul 2006target 2018
Solar project J1284, Linn County
Solar
250 MWWithdrawn / abandoned Linn, IAMISO Apr 2019target 2023
Mirage Solar
Solar
250 MWWithdrawn / abandoned Kern, CACAISO Apr 2012target 2016
Solar project IC-539, Coffee County
Solar
250 MWWithdrawn / abandoned Coffee, GASoutheast Nov 2016
Onshore wind project GEN-2024-202, Hyde County
Onshore wind
250 MWWithdrawn / abandoned Hyde, SDSPP Mar 2025target 2030
Battery storage project J3559, Hancock County
Battery storage
250 MWWithdrawn / abandoned Hancock, KYMISO Apr 2024target 2027
Onshore wind project GEN-2022-048, Woodward County
Onshore wind
250 MWWithdrawn / abandoned Woodward, OKSPP Jun 20222025
Solar project GEN-2023-195, Bailey County
Solar
250 MWWithdrawn / abandoned Bailey, TXSPP Oct 2023target 2028
Solar + storage project 720, Canyon County
Solar + storage
250 MWWithdrawn / abandoned Canyon, IDWest Jun 2023target 2027
Quartzsite Solar Energy
Solar
250 MWWithdrawn / abandoned La Paz, AZCAISO May 2008target 2014
Rancho 2 Energy Storage
Battery storage
250 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2019target 2023
Onshore wind project GEN-2023-093, Morton County
Onshore wind
250 MWWithdrawn / abandoned Morton, KSSPP Oct 2023target 2030
Solar project GEN-2022-040, Stephens County
Solar
250 MWWithdrawn / abandoned Stephens, OKSPP Jun 20222025
Solar project J3862, Deuel County
Solar
250 MWWithdrawn / abandoned Deuel, SDMISO Dec 2024target 2028
Battery storage project GEN-2023-167, Oklahoma County
Battery storage
250 MWWithdrawn / abandoned Oklahoma, OKSPP Oct 2023target 2028
Battery storage project J3580, Mississippi County
Battery storage
250 MWWithdrawn / abandoned Mississippi, ARMISO Apr 2024target 2028
Solar project J2507, Pike County
Solar
250 MWWithdrawn / abandoned Pike, INMISO Sep 2022target 2025
Kettlebail Solar
Solar + storage · Emeren US, LLC
250 MWWithdrawn / abandoned Cortland, NYNYISO May 2023
Solar + storage project Q502, Yavapai County
Solar + storage
250 MWWithdrawn / abandoned Yavapai, AZWest Mar 2023target 2027
Solar + storage project C3-112, Oneida County
Solar + storage
250 MWWithdrawn / abandoned Oneida, IDWest May 2023target 2027
Solar project Q17, Kern County
Solar
250 MWWithdrawn / abandoned Kern, CAWest Dec 2010target 2016
Solar project GEN-2018-073, Floyd County
Solar
250 MWWithdrawn / abandoned Floyd, TXSPP Oct 2018target 2026
Onshore wind project GEN-2023-139, Osborne County
Onshore wind
250 MWWithdrawn / abandoned Osborne, KSSPP Oct 2023target 2028
Solar + storage project Q447, Yavapai County
Solar + storage
250 MWWithdrawn / abandoned Yavapai, AZWest Mar 2022target 2025
Solar + storage project Company 249, Clark County
Solar + storage
250 MWWithdrawn / abandoned Clark, NVWest Mar 2023target 2026
Onshore wind project GEN-2023-068, Stanton County
Onshore wind
250 MWWithdrawn / abandoned Stanton, KSSPP Oct 2023target 2030
Grateful Storage, LLC
Battery storage · Grateful Storage, LLC
250 MWWithdrawn / abandoned Orange, NYNYISO Aug 2024
Onshore wind project GEN-2006-038N009, Knox County
Onshore wind
250 MWWithdrawn / abandoned Knox, NESPP Oct 2006
Battery storage project J2789, Jasper County
Battery storage
250 MWWithdrawn / abandoned Jasper, ILMISO Sep 2022target 2025
Battery storage project LGE-GIS-2021-016, Jefferson County
Battery storage
250 MWWithdrawn / abandoned Jefferson, KYSoutheast Mar 2021target 2024
King Cabbage Solar
Solar · ACE DevCo NC, LLC
250 MWWithdrawn / abandoned ERCOT Feb 2025target 2028
Page 104 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)