SOLAR + STORAGE Β· WESTSolar + storage project C3-112, Oneida County
Solar + storage project C3-112, Oneida County is a 250 MW solar + storage request withdrawn in the West interconnection queue, in Oneida County, Idaho, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C3-112
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Ben Lomond Populus #1 transmission line
- Location
- Oneida County, Idaho
- Technology
- Solar: 250 MW Β· Battery
- Total requested
- 250 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 15 May 2023
- Proposed online date
- December 2027
Location
Marker shows the centre of Oneida County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem