United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
ONSHORE WIND Β· SPPOnshore wind project GEN-2015-092, Grady County
Onshore wind project GEN-2015-092, Grady County is a 250 MW onshore wind request withdrawn in the SPP interconnection queue, in Grady County, Oklahoma, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2015 (completed)
- Withdrawn / abandonedFeb 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2020 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2015-092
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Lawton East Side-Sunnyside (Terry Road) 345kV
- Location
- Grady County, Oklahoma
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 September 2015
- Proposed online date
- December 2020
- Came online
- December 2020
- Withdrawn
- February 2024
Location
Marker shows the centre of Grady County; the queue data does not give exact sites.
Other requests in Grady County
- Solar project GEN-2018-055, Grady CountySolar Β· 252 MW Β· agreement signed
- Solar project GEN-2017-150, Grady CountySolar Β· 250 MW Β· agreement signed
- Onshore wind project GEN-2017-233, Grady CountyOnshore wind Β· 215 MW Β· agreement signed
- Battery storage project GEN-2024-369, Grady CountyBattery storage Β· 250 MW Β· in study
- Battery storage project GEN-2025-SR6, Grady CountyBattery storage Β· 200 MW Β· in study
- Solar project GEN-2023-035, Grady CountySolar Β· 200 MW Β· in study
- Solar project GEN-2022-055, Grady CountySolar Β· 200 MW Β· in study
- Solar + storage project GEN-2024-362, Grady CountySolar + storage Β· 140 MW Β· in study
- Onshore wind project GEN-2014-057, Grady CountyOnshore wind Β· 250 MW Β· built
- Onshore wind project GEN-2007-043, Grady CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project GEN-2011-050, Grady CountyOnshore wind Β· 108 MW Β· built
- Onshore wind project GEN-2014-020, Grady CountyOnshore wind Β· 100 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem