United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

BATTERY STORAGE Β· MISO

Battery storage project J3580, Mississippi County

Battery storage project J3580, Mississippi County is a 250 MW battery storage request withdrawn in the MISO interconnection queue, in Mississippi County, Arkansas, connecting to ARKANSAS ELECTRIC COOPERATIVE CORPORATION.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedMay 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3580
Grid region
MISO (Midcontinent)
Utility / transmission owner
ARKANSAS ELECTRIC COOPERATIVE CORPORATION
Connection point (POI)
AECC Dell 161kV - Nucor-Yamato 161kV Switching Station 161.0kV
Location
Mississippi County, Arkansas
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
18 April 2024
Proposed online date
May 2028
Withdrawn
May 2025

Location

Marker shows the centre of Mississippi County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Mississippi County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem