United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) — page 10

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests · page 10 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3269, Hamilton County
Solar
300 MWWithdrawn / abandoned Hamilton, ILMISO Apr 2024target 2027
Solar project J3562, Vermilion County
Solar
300 MWWithdrawn / abandoned Vermilion, ILMISO Apr 2024target 2028
Solar project J3499, Kosciusko County
Solar
300 MWWithdrawn / abandoned Kosciusko, INMISO Apr 2024target 2028
Onshore wind project J1676, Mclean County
Onshore wind
300 MWWithdrawn / abandoned Mclean, ILMISO Jun 2020target 2023
Battery storage project J2419, Faribault County
Battery storage
300 MWWithdrawn / abandoned Faribault, MNMISO Sep 2022target 2027
Gas project J130, Hancock County
Gas
300 MWWithdrawn / abandoned Hancock, IAMISO Apr 2010target 2011
Other project G116, Knox County
Other
300 MWWithdrawn / abandoned Knox, INMISO Aug 2001target 2005
Solar project J3569, Poinsett County
Solar
300 MWWithdrawn / abandoned Poinsett, ARMISO Apr 2024target 2028
Battery storage project J2504, Coles County
Battery storage
300 MWWithdrawn / abandoned Coles, ILMISO Sep 2022target 2026
Onshore wind project J2327, Lamoure County
Onshore wind
300 MWWithdrawn / abandoned Lamoure, NDMISO Sep 2022target 2026
Solar + storage project J3088, Woodbury County
Solar + storage
300 MWWithdrawn / abandoned Woodbury, IAMISO Sep 2022target 2027
Onshore wind project J1702, Shelby County
Onshore wind
300 MWWithdrawn / abandoned Shelby, ILMISO Jun 2020target 2023
Onshore wind project J3700, Champaign County
Onshore wind
300 MWWithdrawn / abandoned Champaign, ILMISO Apr 2024target 2028
Solar project J2090, Crittenden County
Solar
300 MWWithdrawn / abandoned Crittenden, ARMISO Jul 2022target 2026
Onshore wind project J610, Benton County
Onshore wind
300 MWWithdrawn / abandoned Benton, IAMISO May 2016target 2018
Solar project J3576, Walthall County
Solar
300 MWWithdrawn / abandoned Walthall, MSMISO Apr 2024target 2028
Onshore wind project J977, Jackson County
Onshore wind
300 MWWithdrawn / abandoned Jackson, MNMISO Mar 2018target 2021
Solar project J3958, Sullivan County
Solar
300 MWWithdrawn / abandoned Sullivan, MOMISO Apr 2025target 2029
Battery storage project J3018, Pottawattamie County
Battery storage
300 MWWithdrawn / abandoned Pottawattamie, IAMISO Sep 2022target 2026
Onshore wind project H033, Kandiyohi County
Onshore wind
300 MWWithdrawn / abandoned Kandiyohi, MNMISO May 2008target 2011
Onshore wind project G982, Roberts County
Onshore wind
300 MWWithdrawn / abandoned Roberts, SDMISO Mar 2008target 2009
Solar project J3383, Boone County
Solar
300 MWWithdrawn / abandoned Boone, INMISO Apr 2024target 2028
Onshore wind project J1177, Schuyler County
Onshore wind
300 MWWithdrawn / abandoned Schuyler, MOMISO Mar 2018target 2020
Battery storage project J2724, Shelby County
Battery storage
300 MWWithdrawn / abandoned Shelby, ILMISO Sep 2022target 2027
Battery storage project J2569, St. Louis County
Battery storage
300 MWWithdrawn / abandoned St. Louis, MNMISO Sep 2022target 2026
Onshore wind project G766, Hillsdale County
Onshore wind
300 MWWithdrawn / abandoned Hillsdale, MIMISO Mar 2007target 2011
Onshore wind project G924, Rice County
Onshore wind
300 MWWithdrawn / abandoned Rice, MNMISO Dec 2007target 2009
Solar + storage project J3747, Lonoke County
Solar + storage
300 MWWithdrawn / abandoned Lonoke, ARMISO Apr 2024target 2028
Battery storage project J3264, Otsego County
Battery storage
300 MWWithdrawn / abandoned Otsego, MIMISO Apr 2024target 2028
Solar project J2234, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Onshore wind project J3262, Jefferson County
Onshore wind
300 MWWithdrawn / abandoned Jefferson, TXMISO Apr 2024target 2028
Solar project J1413, Howard County
Solar
300 MWWithdrawn / abandoned Howard, IAMISO Apr 2019target 2022
Onshore wind project G925, Dewitt County
Onshore wind
300 MWWithdrawn / abandoned Dewitt, ILMISO May 2010target 2010
Solar project J2417, Trempealeau County
Solar
300 MWWithdrawn / abandoned Trempealeau, WIMISO Sep 2022target 2027
Onshore wind project J3640, Shiawassee County
Onshore wind
300 MWWithdrawn / abandoned Shiawassee, MIMISO Apr 2024target 2028
Onshore wind project G738, Lincoln County
Onshore wind
300 MWWithdrawn / abandoned Lincoln, MNMISO Feb 2007target 2008
Solar project J3307, Callaway County
Solar
300 MWWithdrawn / abandoned Callaway, MOMISO Apr 2024target 2027
Solar project J1337, Sherburne County
Solar
300 MWWithdrawn / abandoned Sherburne, MNMISO Apr 2019target 2022
Onshore wind project J3920, Clay County
Onshore wind
300 MWWithdrawn / abandoned Clay, IAMISO Mar 2025target 2030
Gas project G416, Washington County
Gas
300 MWWithdrawn / abandoned Washington, MNMISO Mar 2004target 2004
Onshore wind project H014, Rush County
Onshore wind
300 MWWithdrawn / abandoned Rush, INMISO Apr 2008target 2011
Onshore wind project J713, Oliver County
Onshore wind
300 MWWithdrawn / abandoned Oliver, NDMISO Jun 2017target 2020
Onshore wind project J3995, Jasper County
Onshore wind
300 MWWithdrawn / abandoned Jasper, ILMISO Apr 2025target 2030
Gas project J131, Lyon County
Gas
300 MWWithdrawn / abandoned Lyon, MNMISO Apr 2010target 2013
Battery storage project J3693, Marshall County
Battery storage
300 MWWithdrawn / abandoned Marshall, INMISO Apr 2024target 2026
Solar project J3171, Drew County
Solar
300 MWWithdrawn / abandoned Drew, ARMISO Sep 2022target 2026
Solar project J2207, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Gas project J3407, Manistee County
Gas
300 MWWithdrawn / abandoned Manistee, MIMISO Apr 2024target 2028
Solar project J1078, Mississippi County
Solar
300 MWWithdrawn / abandoned Mississippi, ARMISO Mar 2018target 2021
Onshore wind project J100, Henry County
Onshore wind
300 MWWithdrawn / abandoned Henry, ILMISO Dec 2009target 2012
Page 10 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)