United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

BATTERY STORAGE Β· MISO

Battery storage project J2569, St. Louis County

Battery storage project J2569, St. Louis County is a 300 MW battery storage request withdrawn in the MISO interconnection queue, in St. Louis County, Minnesota, connecting to MINNESOTA POWER INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2569
Grid region
MISO (Midcontinent)
Utility / transmission owner
MINNESOTA POWER INC.
Connection point (POI)
Arrowhead 115 kV Substation
Location
St. Louis County, Minnesota
Technology
Battery: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
May 2026
Withdrawn
October 2025

Location

Marker shows the centre of St. Louis County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in St. Louis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem