πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project G660, St. Louis County

Onshore wind project G660, St. Louis County is a 50.0 MW onshore wind request withdrawn in the MISO interconnection queue, in St. Louis County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2006 (completed)
  2. Withdrawn / abandonedFeb 2009 (project stopped here)
  3. ConsentedFeb 2009 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G660
Grid region
MISO (Midcontinent)
Connection point (POI)
Minntac 115 kV Substation
Location
St. Louis County, Minnesota
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
17 July 2006
Agreement signed
9 February 2009
Proposed online date
January 2008
Withdrawn
February 2009

Location

Marker shows the centre of St. Louis County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in St. Louis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem