Projects
| Project | Capacity | Stage |
|---|---|---|
| Rowancraig Wind Farm Onshore wind · Koehler Renewable Energy UK Limited |
40 MW | Scoping |
| Middleton Farm Solar Solar · Bluestone Middleton Farm 1 Ltd |
39 MW | Scoping |
| Craigdow Hill Wind Farm Onshore wind · Abei Energy Limited |
38 MW | Scoping |
| Craig Nab Wind Energy Hub Wind + storage · Craig Nab Wind Energy Hub Limited |
36 MW | Scoping |
| Hawkwood Wind Farm Onshore wind · Wilson Renewables IV LLP |
34 MW | Scoping |
| Lorg Extension Wind Farm Onshore wind · RWE Renewables UK Onshore Wind Limited |
33 MW | Scoping |
| Drummarnock Wind Farm Onshore wind · Drummarnock Wind Farm Limited |
30 MW | Scoping |
| Meiklelaught Farm BESS Battery storage · GPC 1127 Ltd |
30 MW | Scoping |
| Ardoch Farm Battery Storage Battery storage · Capbal (Kilwinning) Limited |
27 MW | Scoping |
| Bankhead 25MW BESS Battery storage · GPC 1169 Ltd |
25 MW | Scoping |
| Elvanfoot (25MW) Energy Storage Battery storage · Elvanfoot Energy Storage 3 Limited |
25 MW | Scoping |
| Windy Standard 1 Repower Onshore wind · Fred Olsen Renewables Limited |
22 MW | Scoping |
| Brae WF Wind + storage · Wind 2 Limited |
20 MW | Scoping |
| Lamford Hill Solar + storage · Benbrack Wind Farm Limited |
20 MW | Scoping |
| Dealanach WLC WF Onshore wind · Dealanach Limited |
12 MW | Scoping |
| Dersalloch Wind Farm Extension Battery storage · Scottish Power Renewables (UK) Limited |
11 MW | Scoping |
| Enoch Hill 2 Wind Farm Wind + storage · RWE Renewables UK Onshore Wind Limited |
10 MW | Awaiting Consents |
| Hunterston Hydrogen Hydro and pumped storage · Statkraft Hydrogen UK Holding Limited |
5 MW | Scoping |
| Fife Grid Services Other · Kincardine Grid 3 Ltd |
0 MW | Scoping |
Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.