Grid infrastructure β€Ί Connection queue β€Ί Wind + storage

WIND + STORAGE Β· SPT

Brae WF

Brae WF is a 20 MW wind + storage project in planning, connecting to the SP Transmission (south Scotland) network at Linnmill GSP, with capacity due from August 2032. The connection agreement is held by Wind 2 Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Aug 2032 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004633
Customer
Wind 2 Limited
Technology
Energy Storage System, Wind Onshore
Total capacity
20 MW
Change in this agreement
+20 MW
Capacity effective from
30 August 2032
Connection site
Linnmill GSP
Transmission owner
SP Transmission (south Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Linnmill GSP Β· Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem