Grid infrastructure › Connection queue › Other

OTHER · SPT

Fife Grid Services

Fife Grid Services is a 0 MW other project in planning, connecting to the SP Transmission (south Scotland) network at Fife Grid Services Facility 275kV Substation, with capacity due from July 2027. The connection agreement is held by Kincardine Grid 3 Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-000453
Customer
Kincardine Grid 3 Ltd
Technology
Reactive Compensation
Total capacity
0 MW
Capacity effective from
30 July 2027
Connection site
Fife Grid Services Facility 275kV Substation
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near Fife Grid Services Facility · Grid map

Other projects at Fife Grid Services Facility 275kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem