Grid infrastructure › Connection queue › Wind + storage
WIND + STORAGE · SPTEnoch Hill 2 Wind Farm
Enoch Hill 2 Wind Farm is a 10 MW wind + storage project in planning, connecting to the SP Transmission (south Scotland) network at Enoch Hill 2 Wind Farm 33kV Substation, with capacity due from April 2027. The connection agreement is held by RWE Renewables UK Onshore Wind Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Apr 2027 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-000478
- Customer
- RWE Renewables UK Onshore Wind Limited
- Technology
- Energy Storage System, Wind Onshore
- Total capacity
- 10 MW
- Change in this agreement
- +10 MW
- Capacity effective from
- 30 April 2027
- Connection site
- Enoch Hill 2 Wind Farm 33kV Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Awaiting Consents
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem