Projects shown968461.1 GW in total
In planning968scoping or awaiting consent
Consented or building149closest to connecting
Built212connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

968 projects · page 19 of 20
ProjectCapacityStageConnection siteFrom
Noventum Hawthorn Pit
Solar + storage · Noventum Power Solar 2 Limited
57 MWScoping Wearside Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2035
Oldbury (Tertiary)
Battery storage · Pivoted Power LLP
57 MWAwaiting Consents Oldbury 275kV Substation
National Grid (England & Wales)
Oct 2037
Penwortham BESS
Battery storage · Cse28 Limited
57 MWScoping Penwortham 400kV Substation
National Grid (England & Wales)
Jun 2031
Pivot Power Harker Hybrid
Solar + storage · Pivoted Power LLP
57 MWScoping Harker 400/132KV Substation
National Grid (England & Wales)
Oct 2029
Plas Power Estate North Tertiary
Solar + storage · Lightsource Spv 192 Limited
57 MWScoping Legacy 400kV Substation
National Grid (England & Wales)
May 2028
Rayleigh 2 Tertiary
Solar + storage · Enso Green Holdings J Limited
57 MWScoping Rayleigh Main 400kV Substation
National Grid (England & Wales)
Oct 2028
Walpole
Solar + storage · Hollygreen Energyfarm Limited
57 MWScoping Walpole 400kV substations
National Grid (England & Wales)
Oct 2030
Walpole 1 (Tertiary)
Solar + storage · Walpole Green Limited
57 MWScoping Walpole 400kV Substation
National Grid (England & Wales)
Aug 2025
Willington
Battery storage · Pivoted Power LLP
57 MWScoping Willington East 400kV Substation
National Grid (England & Wales)
Jun 2026
Bicker Fen 2 Solar
Solar + storage · Agr Solar 3 Limited
50 MWAwaiting Consents Bicker Fen 400kV Substation
National Grid (England & Wales)
Jul 2026
Rugeley
Battery storage · Rugeley Power Generation Limited
50 MWScoping Rugeley GSP
National Grid (England & Wales)
Oct 2032
JBM Solar 12 - Shrewsbury Solar
Solar + storage · RWE Renewables UK Solar and Storage Limited
50 MWScoping Shrewsbury 400/33kV Substation
National Grid (England & Wales)
Sep 2028
Harrington Franklin Limited
Battery storage · Edp Renewables UK Limited
50 MWAwaiting Consents Richborough GSP
National Grid (England & Wales)
Oct 2025
Alverdiscott
Battery storage · Pivoted Power LLP
50 MWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Aug 2031
Axminster
Battery storage · Pivoted Power LLP
50 MWScoping Axminster 400kV Substation
National Grid (England & Wales)
Oct 2027
Biggleswade PV
Solar + storage · Cse38 Limited
50 MWAwaiting Consents Biggleswade 400kV Substation
National Grid (England & Wales)
Oct 2031
Bolney BESS
Battery storage · Cse45 Limited
50 MWScoping DRAGON GREEN 400kV SUBSTATION
National Grid (England & Wales)
Sep 2037
Chirton Grange
Solar + storage · Elawan Energy UK Limited
50 MWScoping Tynemouth GSP (NPG)
National Grid (England & Wales)
Oct 2035
Eaton Socon PV Storage
Solar + storage · CSE37 Limited
50 MWScoping Eaton Socon 400kV Substation
National Grid (England & Wales)
Oct 2029
EMERGE Centre
Other · Uniper UK Limited
50 MWScoping Ratcliffe-On-Soar 132kV Substation
National Grid (England & Wales)
Jun 2029
Exeter (Tertiary)
Solar + storage · Pivoted Power LLP
50 MWAwaiting Consents Exeter 400kV Substation
National Grid (England & Wales)
Jun 2028
Iver
Battery storage · Juniper Energy Limited
50 MWScoping Iver 275kV Substation
National Grid (England & Wales)
Oct 2027
JBM Solar 13 - Melksham
Solar + storage · Jbm Solar Projects 13 Limited
50 MWScoping Melksham 400kV Substation
National Grid (England & Wales)
Jul 2026
Kearsley
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents Kearsley 275kV Substation
National Grid (England & Wales)
Oct 2028
Kingsfold
Solar + storage · Greentech Projects Holding UK Limited
50 MWScoping Bolney GSP
National Grid (England & Wales)
Oct 2037
Laleham
Battery storage · Juniper Energy Limited
50 MWScoping Laleham 132kV Substation
National Grid (England & Wales)
May 2028
Little Horsted
Solar + storage · Cse34 Limited
50 MWScoping Little Horsted GSP
National Grid (England & Wales)
Oct 2031
Lovedean Greener Grid Park
Battery storage · Statkraft UK Ltd
50 MWScoping Lovedean 400kV Substation
National Grid (England & Wales)
Jun 2028
Ninfield Greener Grid Park
Battery storage · Ninfield Grid Solutions Limited
50 MWAwaiting Consents Ninfield 400kV Substation
National Grid (England & Wales)
Jan 2031
NorthFleet Tertiary
Solar + storage · Cse29 Limited
50 MWScoping Northfleet East 400kV Substation
National Grid (England & Wales)
Jun 2028
Oldbury (Tertiary)
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents Oldbury 275kV Substation
National Grid (England & Wales)
Jun 2027
Seabank (Tertiary)
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents SEABANK 400/33kV SUBSTATION
National Grid (England & Wales)
Nov 2023
Sellindge (Tertiary)
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents Sellindge 400kV Substation
National Grid (England & Wales)
Oct 2028
Spennymoor
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents Spennymoor 400kV Substation
National Grid (England & Wales)
Oct 2028
Spennymoor PV & BESS
Solar + storage · Cse27 Limited
50 MWScoping Spennymoor 400kV Substation
National Grid (England & Wales)
Jul 2032
Swansea North
Battery storage · Edf Energy Renewables Limited
50 MWScoping Swansea North 400kV Substation
National Grid (England & Wales)
Jul 2028
Taunton
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents Taunton 400kV Substation
National Grid (England & Wales)
Oct 2031
Whitson
Battery storage · Pivoted Power LLP
50 MWScoping Whitson 275kV Substation
National Grid (England & Wales)
Oct 2027
Petre Street
Battery storage · Mercia Power Response Limited
50 MWScoping Pitsmoor GSP
National Grid (England & Wales)
Oct 2034
Bolney
Solar + storage · Pivoted Power LLP
48 MWScoping Bolney 400kV Substation
National Grid (England & Wales)
Jan 2031
Fleet Tertiary
Gas · Fleet Solar Limited
48 MWScoping Fleet 400kV Substation
National Grid (England & Wales)
Aug 2028
JBM Solar -Minety
Solar + storage · Jbm Solar Projects 14 Ltd
48 MWScoping Minety 400kV Substation
National Grid (England & Wales)
Nov 2028
Mannington
Solar + storage · Baywa R.e. UK Limited
48 MWScoping Mannington 400kV Substation
National Grid (England & Wales)
Apr 2028
NatPower Llanteg Green Energy Park
Battery storage · Np Spv 30 Limited
48 MWScoping South Wales West Connection Node C 400kV
National Grid (England & Wales)
Dec 2037
Southfields
Solar + storage · PD688IRO LTD
48 MWAwaiting Consents Minety 400kV Substation
National Grid (England & Wales)
Jun 2025
Willington East 1 (Tertiary)
Solar + storage · Enso Green Holdings U Limited
48 MWScoping Willington East 400kV Substation
National Grid (England & Wales)
Oct 2027
Willington East 2 (Tertiary)
Solar + storage · Enso Green Holdings Ss Limited
48 MWScoping Willington East 400kV Substation
National Grid (England & Wales)
Jul 2028
Blaen y Glyn
Onshore wind · Banc Du Energy Park Limited
46 MWScoping Chirk GSP
National Grid (England & Wales)
Feb 2027
Claydon Solar B (A033)
Solar + storage · RWE Renewables UK Solar and Storage Limited
45 MWScoping Port Ham GSP
National Grid (England & Wales)
Apr 2025
Balgray Wind Farm
Wind + storage · Fred Olsen Renewables Limited
43 MWScoping Dumfries North 400/132kV substation
National Grid (England & Wales)
Oct 2037
Page 19 of 20

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.