United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESOnshore wind interconnection queue in the USA (2023 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Hecate Energy Orem Wind Onshore wind ยท Hecate Energy LLC |
1,542 MW | In study |
| Hecate Energy Arkansas Wind Onshore wind ยท Hecate Energy Gulf Wind LLC |
1,029 MW | In study |
| Hecate Energy Jamaica Wind Onshore wind ยท Hecate Energy LLC |
1,029 MW | In study |
| Meitner Wind Onshore wind ยท IP Meitner, LLC |
709 MW | Agreement signed |
| Aurelius 3 Wind Onshore wind ยท IP Roman III, LLC |
623 MW | In study |
| Aurelius 2 Wind Onshore wind ยท IP Roman Wind II, LLC |
622 MW | In study |
| Aurelius Wind Onshore wind ยท IP Roman Wind, LLC |
622 MW | Agreement signed |
| White Oak King Wind Onshore wind ยท KSK Wind Farm 1, LLC |
607 MW | In study |
| Onshore wind project G0953, Lincoln County Onshore wind |
600 MW | In study |
| Dundee East A Wind Onshore wind ยท Felix 2, LLC |
524 MW | Agreement signed |
| Onshore wind project G0861, Deschutes County Onshore wind |
500 MW | In study |
| Onshore wind project G0870, Lake County Onshore wind |
500 MW | In study |
| Onshore wind project G0871, Lake County Onshore wind |
500 MW | In study |
| Onshore wind project Q539, Coconino County Onshore wind |
500 MW | In study |
| Onshore wind project Q538, Coconino County Onshore wind |
500 MW | In study |
| Onshore wind project GI-2023-14, Morgan County Onshore wind |
400 MW | Paused / redesign |
| Onshore wind project GI-TC-2024-16, Laramie County Onshore wind |
400 MW | Agreement signed |
| Onshore wind project G0956, Benewah County Onshore wind |
400 MW | In study |
| Channing Wind Onshore wind |
361 MW | Paused / redesign |
| Onshore wind project GEN-2022-161, Butler County Onshore wind |
360 MW | In study |
| Onshore wind project G0955, Lincoln County Onshore wind |
350 MW | In study |
| Onshore wind project G0954, Lincoln County Onshore wind |
350 MW | In study |
| Laurel Wind Energy Center Onshore wind ยท LAUREL ENERGY CENTER, LLC |
307 MW | Agreement signed |
| WOE Gyp King Wind Onshore wind ยท KSK Wind Farm 1, LLC |
304 MW | Paused / redesign |
| Onshore wind project Q497, Navajo County Onshore wind |
300 MW | In study |
| Onshore wind project G0872, Garfield County Onshore wind |
300 MW | In study |
| Onshore wind project G0918, Lane County Onshore wind |
300 MW | In study |
| Onshore wind project G0973, Mason County Onshore wind |
300 MW | In study |
| Onshore wind project GEN-2023-107, Finney County Onshore wind |
300 MW | In study |
| Onshore wind project G0972, Curry County Onshore wind |
300 MW | In study |
| Onshore wind project G0994, Sherman County Onshore wind |
277 MW | In study |
| Dundee East B Wind Onshore wind ยท Felix 2, LLC |
261 MW | Agreement signed |
| Goodnight Wind II Onshore wind ยท FGE Goodnight II, LLC |
259 MW | Agreement signed |
| Onshore wind project MPC04500, Grand Forks County Onshore wind |
258 MW | In study |
| Shamrock II Wind Onshore wind |
257 MW | Paused / redesign |
| LH252W Onshore wind |
252 MW | Agreement signed |
| Onshore wind project G1013, Umatilla County Onshore wind |
250 MW | In study |
| Onshore wind project 23-226, Jefferson County Onshore wind |
250 MW | In study |
| Onshore wind project 438, Stillwater County Onshore wind |
250 MW | Paused / redesign |
| Onshore wind project 23-227, Jefferson County Onshore wind |
250 MW | In study |
| Onshore wind project 23-228, Jefferson County Onshore wind |
250 MW | In study |
| Onshore wind project 23-231, Jefferson County Onshore wind |
250 MW | In study |
| Onshore wind project G0974, Wasco County Onshore wind |
250 MW | In study |
| Onshore wind project G1036, Hood River County Onshore wind |
234 MW | In study |
| Onshore wind project GEN-2023-229, Caddo County Onshore wind |
230 MW | In study |
| Aquilla Lake 3 Wind (Alternative POI Oncor 138KV) Onshore wind |
226 MW | Paused / redesign |
| Aquilla Lake 3 Wind ( Alternative POI Oncor 345kV) Onshore wind |
226 MW | Paused / redesign |
| Onshore wind project CS23-06, Whitman County Onshore wind |
221 MW | Agreement signed |
| Onshore wind project GEN-2022-176, Nowata County Onshore wind |
215 MW | In study |
| Supra Wind Onshore wind ยท NextEra Energy Interconnection Holdings, LLC |
206 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)44 ยท 11.4 GW
- ERCOT (Texas)31 ยท 11.1 GW
- SPP (Southwest Power Pool)7 ยท 1,522 MW
- PJM (Mid-Atlantic, Midwest)7 ยท 577 MW
- MISO (Midcontinent)1 ยท 258 MW
- CAISO (California)1 ยท 108 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)