Solar interconnection queue in the USA (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown37946.1 GW
Active in queue46.1 GW379 requests
Agreement signed6,242 MW32 requests
Withdrawn49769.0 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

379 requests ยท page 1 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Aurelius Solar
Solar ยท IP Roman, LLC
1,124 MWAgreement signed Deaf Smith, TXERCOT Jul 2023target 2028
Rocking X Solar
Solar ยท 7100 Tin Top LLC
602 MWIn study Parker, TXERCOT Oct 2023target 2027
Soledad Solar
Solar
562 MWIn study Kern, CACAISO Apr 2023target 2028
Domestic Chicken
Solar
559 MWIn study Maricopa, AZCAISO Apr 2023target 2029
La Salle Solar
Solar ยท La Salle Solar LLC
513 MWAgreement signed La Salle, TXERCOT Apr 2023target 2027
Torbino Solar
Solar
507 MWIn study Kern, CACAISO Apr 2023target 2029
Titus Sienta Solar
Solar ยท Sol Sienta Solar, LLC
502 MWIn study Pecos, TXERCOT Oct 2023target 2028
Solar project G1032, Grant County
Solar
500 MWIn study Grant, WAWest Nov 2023target 2028
Solar project IC-1147, Monroe County
Solar
500 MWPaused / redesign Monroe, GASoutheast Jun 2023target 2030
Solar project G1015, Benton County
Solar
500 MWIn study Benton, WAWest Nov 2023target 2029
Aurelius 2 Solar
Solar ยท IP Roman, LLC
445 MWIn study Deaf Smith, TXERCOT Dec 2023target 2028
Aurelius 3 Solar
Solar ยท IP Roman III, LLC
445 MWIn study Deaf Smith, TXERCOT Dec 2023target 2029
Whiskey Diggings
Solar
414 MWIn study Sutter, CACAISO Apr 2023target 2030
Silverton Solar
Solar ยท NextEra Energy Interconnection Holdings, LLC
410 MWIn study Briscoe, TXERCOT Dec 2023target 2029
Solar project G1035, Douglas County
Solar
400 MWIn study Douglas, WAWest Nov 2023target 2028
Solar project G1016, Klickitat County
Solar
400 MWIn study Klickitat, WAWest Nov 2023target 2029
Tetris Solar
Solar ยท NextEra Energy Interconnection Holdings LLC
359 MWIn study Zapata, TXERCOT Jul 2023target 2029
Tetris Solar (Alternative POI)
Solar
359 MWPaused / redesign Zapata, TXERCOT Jul 2023target 2028
Funston Solar (AEP POI)
Solar
355 MWPaused / redesign Jones, TXERCOT Sep 2023target 2028
Goldlink
Solar
354 MWIn study Nye, NVCAISO Apr 2023target 2030
Bajada
Solar
353 MWIn study Riverside, CACAISO Apr 2023target 2030
Lucy Solar
Solar ยท Concho County Solar 1 LLC
352 MWAgreement signed Concho, TXERCOT Jun 2023target 2027
Argos Solar
Solar
352 MWIn study San Bernardino, CACAISO Apr 2023target 2030
Titus Low Carbon Ventures Solar 1
Solar ยท Vaquero Solar, LLC
338 MWIn study San Patricio, TXERCOT Oct 2023target 2028
Solar project GEN-2023-015, Finney County
Solar
330 MWIn study Finney, KSSPP Oct 2023target 2026
Solar project J1598, Calcasieu Parish County
Solar
325 MWAgreement signed Calcasieu Parish, LAMISO Dec 2023target 2026
Green Palms
Solar
307 MWIn study Riverside, CACAISO Apr 2023target 2030
Serenity
Solar
305 MWIn study Nye, NVCAISO Apr 2023target 2031
Gosford Solar Storage
Solar
305 MWIn study Kern, CACAISO Apr 2023target 2029
Whitewright Solar 2
Solar ยท SunWR, LLC
302 MWIn study Grayson, TXERCOT Dec 2023target 2028
Solar project G0866, Sherman County
Solar
300 MWIn study Sherman, ORWest Jun 2023target 2027
Solar project GEN-2023-099, Jackson County
Solar
300 MWIn study Jackson, KSSPP Oct 2023target 2030
AW300S
Solar
300 MWAgreement signed Sierra, NMWest Mar 2023target 2029
Solar project IA-PNM-2023-07, Santa Fe County
Solar
300 MWIn study Santa Fe, NMWest Jan 2023target 2025
Solar project 737, Bingham County
Solar
280 MWIn study Bingham, IDWest Sep 2023target 2027
Solar project 923973, Richmond County
Solar ยท Masked
275 MWIn study Richmond, NCSoutheast Sep 2023
Solar project AI2-081, Logan County
Solar
271 MWIn study Logan, OHPJM Feb 2023target 2025
Santa Garcias Solar
Solar ยท Oxy Renewable Energy LLC
265 MWIn study Kleberg, TXERCOT Jun 2023target 2028
Solar project G0944, Morrow County
Solar
261 MWIn study Morrow, ORWest Oct 2023target 2026
Lazy U Solar 2
Solar ยท Lazy U Solar 2
252 MWIn study Hardeman, TXERCOT Aug 2023target 2029
Lazy U Solar 1
Solar ยท Lazy U Solar 1
252 MWIn study Hardeman, TXERCOT Aug 2023target 2029
Clutch City Solar Phase II
Solar ยท HZ SOLAR I, LLC
251 MWAgreement signed Brazoria, TXERCOT Feb 2023target 2028
Solar project G1031, Klickitat County
Solar
250 MWIn study Klickitat, WAWest Nov 2023target 2028
Solar project GEN-2023-220, Osage County
Solar
250 MWIn study Osage, KSSPP Oct 2023target 2029
Solar project GEN-2023-221, Osage County
Solar
250 MWIn study Osage, KSSPP Oct 2023target 2029
Solar project 536, Muhlenberg County
Solar
250 MWIn study Muhlenberg, KYSoutheast Mar 2023target 2026
Solar project IC-1149, Mitchell County
Solar
250 MWPaused / redesign Mitchell, GASoutheast Jul 2023target 2028
Solar project GEN-2022-214, Sumner County
Solar
239 MWIn study Sumner, KSSPP Mar 2023target 2028
Solar project IC-1206, Laurens County
Solar
225 MWAgreement signed Laurens, GASoutheast Nov 2023target 2028
Solar project G0935, Walla Walla County
Solar
225 MWIn study Walla Walla, WAWest Sep 2023target 2027
Page 1 of 8

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)