🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kentucky

SOLAR · SOUTHEAST

Solar project 536, Muhlenberg County

Solar project 536, Muhlenberg County is a 250 MW solar request in interconnection study in the Southeast interconnection queue, in Muhlenberg County, Kentucky, connecting to Tennessee Valley Authority.

Queue statusIn planning
  1. PlanningQueued Mar 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
536
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tennessee Valley Authority
Connection point (POI)
Lost City, KY 161-kV Switching Station
Location
Muhlenberg County, Kentucky
Technology
Solar: 250 MW
Total requested
250 MW
Study phase
Facility Study
Queue status
Active
Entered queue
28 March 2023
Proposed online date
August 2026

Location

Marker shows the centre of Muhlenberg County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Muhlenberg County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem