United States › Grid › Interconnection queues › Kentucky

OTHER · SOUTHEAST

Other project 24, Muhlenberg County

Other project 24, Muhlenberg County is a 48.0 MW other request built and operating in the Southeast interconnection queue, in Muhlenberg County, Kentucky, connecting to Tennessee Valley Authority.

Queue statusOperating
  1. PlanningQueued Jul 1998 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
24
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tennessee Valley Authority
Location
Muhlenberg County, Kentucky
Technology
Other: 48.0 MW
Total requested
48.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
21 July 1998

Location

Marker shows the centre of Muhlenberg County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Muhlenberg County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem