United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown808106.0 GW
Active in queue4,539 MW21 requests
Agreement signed2,971 MW15 requests
Withdrawn808106.0 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

808 requests ยท page 1 of 17
ProjectCapacityStatusLocationRegionQueuedOnline
Pathfinder Renewable Wind Energy
Onshore wind
3,000 MWWithdrawn / abandoned Platte, WYCAISO Mar 2011target 2020
Onshore wind project J236, White County
Onshore wind
2,400 MWWithdrawn / abandoned White, INMISO Dec 2011target 2018
Cowboy Mesa Wind
Onshore wind
1,700 MWWithdrawn / abandoned Lincoln, NMCAISO Mar 2011target 2016
Gas project X2-082, Chesterfield County
Gas
1,575 MWWithdrawn / abandoned Chesterfield, VAPJM Jul 2011target 2015
Onshore wind project X1-020, Cass County
Onshore wind
1,500 MWWithdrawn / abandoned Cass, INPJM Feb 2011target 2018
Eagle Mountain Pump Storage #3
Hydro
1,400 MWWithdrawn / abandoned Riverside, CACAISO Mar 2011target 2017
Gas project 110, Pasco County
Gas ยท Duke Energy Florida, LLC
1,400 MWWithdrawn / abandoned Pasco, FLSoutheast Jul 2011target 2018
Gas project 109, Pasco County
Gas ยท Duke Energy Florida, LLC
1,400 MWWithdrawn / abandoned Pasco, FLSoutheast Jul 2011target 2016
Suncrest Imperial Segs
Solar
1,080 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2015
Central Valley I Segs
Solar
1,080 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
Coal project GEN-2011-030, Finney County
Coal
1,020 MWWithdrawn / abandoned Finney, KSSPP Mar 2011target 2017
Gas project X1-013, Lebanon County
Gas
1,018 MWWithdrawn / abandoned Lebanon, PAPJM Feb 2011target 2015
Kern Solar Ranch (Fka California Solar Ranch)
Solar
1,000 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2018
Gas project X3-102, Charles County
Gas
971 MWWithdrawn / abandoned Charles, MDPJM Oct 2011target 2016
Gas project X3-103, Charles County
Gas
971 MWWithdrawn / abandoned Charles, MDPJM Oct 2011target 2016
Gas project IC-253, Upson County
Gas
968 MWWithdrawn / abandoned Upson, GASoutheast Apr 2011
Gas project IC-248, Upson County
Gas
968 MWWithdrawn / abandoned Upson, GASoutheast Feb 2011
Gas project IC-252, Lee County
Gas
968 MWWithdrawn / abandoned Lee, ALSoutheast Feb 2011
Gas project 111, Citrus County
Gas ยท Duke Energy Florida, LLC
950 MWWithdrawn / abandoned Citrus, FLSoutheast Jul 2011target 2018
Gas project 112, Suwannee County
Gas ยท Masked
950 MWWithdrawn / abandoned Suwannee, FLSoutheast Jul 2011target 2018
Mattawoman Energy
Gas
894 MWWithdrawn / abandoned Prince George's, MDPJM Oct 2011target 2022
Gas project LGE-GIS-2011-004, Mercer County
Gas
880 MWWithdrawn / abandoned Mercer, KYSoutheast May 2011target 2018
Gas project X2-030, Charles County
Gas
830 MWWithdrawn / abandoned Charles, MDPJM May 2011target 2016
Gas project X4-020, York County
Gas
800 MWWithdrawn / abandoned York, PAPJM Nov 2011target 2017
WSP 3
Solar
800 MWWithdrawn / abandoned Kings, CACAISO Mar 2011target 2018
Gas project X4-026, Prince George's County
Gas
792 MWWithdrawn / abandoned Prince George's, MDPJM Nov 2011target 2015
Gas project IC-255, Jackson County
Gas
782 MWWithdrawn / abandoned Jackson, GASoutheast Jun 2011
Gas project IC-250, Upson County
Gas
782 MWWithdrawn / abandoned Upson, GASoutheast Feb 2011
Combined Cycle
Gas
745 MWWithdrawn / abandoned Fairfield, CTISO-NE Jun 2011target 2016
Gas project X3-089, Middlesex County
Gas
744 MWWithdrawn / abandoned Middlesex, NJPJM Oct 2011target 2016
Gas project W4-044, Charles County
Gas
725 MWWithdrawn / abandoned Charles, MDPJM Jan 2011target 2015
Offshore wind project X1-017, Atlantic County
Offshore wind
720 MWWithdrawn / abandoned Atlantic, NJPJM Feb 2011target 2016
Gas project X2-050, Essex County
Gas
705 MWWithdrawn / abandoned Essex, NJPJM Jun 2011target 2016
CVH Power II
Solar
700 MWWithdrawn / abandoned Maricopa, AZCAISO Mar 2011target 2014
Solar project Q17, Maricopa County
Solar
700 MWWithdrawn / abandoned Maricopa, AZWest Apr 2011target 2014
Gas project X3-068, York County
Gas
678 MWWithdrawn / abandoned York, PAPJM Oct 2011target 2017
Gas project J215, St. Joseph County
Gas
670 MWWithdrawn / abandoned St. Joseph, INMISO Jun 2011target 2014
Gas project 228, Anderson County
Gas
640 MWWithdrawn / abandoned Anderson, TNSoutheast Sep 2011
Gas project X3-051
Gas
610 MWWithdrawn / abandoned OHPJM Sep 2011target 2017
Onshore wind project J212, Ward County
Onshore wind
600 MWWithdrawn / abandoned Ward, NDMISO Apr 2011target 2012
CC Administrative Increase
Gas
550 MWWithdrawn / abandoned Hampden, MAISO-NE Aug 2011
Jasper Segs (Fka Sonoran West II)
Solar
540 MWWithdrawn / abandoned San Bernardino, CACAISO Mar 2011target 2016
Hidden Hills Ranch
Solar
540 MWWithdrawn / abandoned Nye, NVCAISO Mar 2011target 2014
Central Valley II Segs
Solar
540 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
Gas project 403, Sevier County
Gas
525 MWWithdrawn / abandoned Sevier, UTWest Oct 2011target 2014
Gas project IC-247, Upson County
Gas
520 MWWithdrawn / abandoned Upson, GASoutheast Feb 2011
Gas project IC-251, Lee County
Gas
520 MWWithdrawn / abandoned Lee, ALSoutheast Feb 2011
Gas project X3-076, Fauquier County
Gas
510 MWWithdrawn / abandoned Fauquier, VAPJM Oct 2011target 2015
Solar Four
Solar
510 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2017
Alta 15
Onshore wind
502 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2014
Page 1 of 17

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)