Cowboy Mesa Wind

Cowboy Mesa Wind is a 1,700 MW onshore wind request withdrawn in the CAISO interconnection queue, in Lincoln County, New Mexico, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedAug 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
689
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Four Corners Sub 345kV Bus
Location
Lincoln County, New Mexico
Technology
Wind: 1,700 MW
Total requested
1,700 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
May 2016
Withdrawn
August 2011

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.