United States › Grid › Interconnection queues › Virginia

OCTARY USA · INTERCONNECTION QUEUES

Solar interconnection queue in Virginia

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown15813.7 GW
Active in queue13.7 GW158 requests
Agreement signed5,292 MW54 requests
Withdrawn47430.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

158 requests · page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Blackwater Solar
Solar
800 MWAgreement signed Sussex, VAPJM Sep 2018target 2029
Randolph Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
500 MWAgreement signed Halifax, VAPJM Dec 2019target 2032
Solar project AG2-570, Brunswick County
Solar · Zeus Energy, LLC
400 MWIn study Brunswick, VAPJM Mar 2025target 2024
Solar project AG2-436, Sussex County
Solar · Monarch Solar, LLC
350 MWIn study Sussex, VAPJM Apr 2025target 2023
Chickahominy Solar 1 and 2
Solar
320 MWAgreement signed Charles City, VAPJM Oct 20162021
Honeybee Solar, LLC
Solar · Honeybee Solar Energy, LLC
301 MWIn study Brunswick, VAPJM Jan 2025target 2025
Solar project AI1-203, Lunenburg County
Solar
300 MWIn study Lunenburg, VAPJM Sep 2022target 2027
Solar project AH2-322, Pittsylvania County
Solar
290 MWIn study Pittsylvania, VAPJM Mar 2022target 2025
Solar project AH2-069, Wythe County
Solar
250 MWIn study Wythe, VAPJM Jan 2022target 2025
Sycamore Cross Solar
Solar
240 MWAgreement signed Isle Of Wight, VAPJM Mar 2017target 2026
Axton Solar
Solar
201 MWPaused / redesign Henry, VAPJM Mar 2019target 2025
Solar project AG2-182, Frederick County
Solar · ACE Development Company, LLC
200 MWIn study Frederick, VAPJM Feb 2025target 2022
Solar project AG2-077, Charlotte County
Solar · Virginia Electric and Power Company
200 MWIn study Charlotte, VAPJM Jan 2025target 2024
Courthouse Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
167 MWIn study Charlotte, VAPJM Mar 2020target 2031
Spring Grove Solar II
Solar
150 MWAgreement signed Surry, VAPJM Jun 2017target 2025
Blue Ridge Solar
Solar
150 MWAgreement signed Pittsylvania, VAPJM Aug 2018target 2028
Pulaski Solar
Solar
150 MWAgreement signed Pulaski, VAPJM Jan 2020target 2028
Solar project AH2-350, Cumberland County
Solar
150 MWIn study Cumberland, VAPJM Mar 2022target 2025
Solar project AG2-069, Brunswick County
Solar · Virginia Electric and Power Company
150 MWIn study Brunswick, VAPJM Feb 2025target 2025
Wild Indigo Solar
Solar
150 MWPaused / redesign Surry, VAPJM Oct 2017target 2026
Solar project AI2-038, Spotsylvania County
Solar
150 MWIn study Spotsylvania, VAPJM Jan 2023target 2027
Solar project AG2-581, Brunswick County
Solar · Bellflower Holdings, LLC
150 MWIn study Brunswick, VAPJM Jan 2025target 2024
Big Pine Solar
Solar
150 MWAgreement signed Sussex, VAPJM Feb 2019target 2031
Riverstone Solar
Solar
150 MWAgreement signed Buckingham, VAPJM Sep 2018target 2027
Maroon Solar
Solar
149 MWPaused / redesign Culpeper, VAPJM Sep 2018target 2027
Enclave Solar Energy Center
Solar
149 MWPaused / redesign Sussex, VAPJM Jan 2019target 2027
Solar project AI2-037, King And Queen County
Solar
142 MWIn study King And Queen, VAPJM Jan 2023target 2027
Solar project AH2-349, Halifax County
Solar
142 MWIn study Halifax, VAPJM Mar 2022target 2025
Solar project AG2-442, Charlotte County
Solar · Taro Solar LLC
140 MWIn study Charlotte, VAPJM Apr 2025target 2024
Woodridge Solar
Solar
138 MWAgreement signed Albemarle, VAPJM Feb 2019target 2027
Solar project AG2-152, Pittsylvania County
Solar · Virginia Electric and Power Company
131 MWIn study Pittsylvania, VAPJM Mar 2025target 2024
Red Brick Solar
Solar
130 MWAgreement signed Lunenburg, VAPJM Dec 2017target 2026
Solar project AI1-145, Prince Edward County
Solar
125 MWIn study Prince Edward, VAPJM Sep 2022target 2026
Solar project AI1-124, Lunenburg County
Solar
125 MWIn study Lunenburg, VAPJM Sep 2022target 2026
Quarter Horse Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
125 MWAgreement signed Charlotte, VAPJM Sep 2020target 2031
Southern Virginia Solar
Solar
125 MWAgreement signed Pittsylvania, VAPJM Jul 2019target 2027
CC Solar I
Solar
120 MWPaused / redesign Caroline, VAPJM Sep 2018target 2025
Chester Solar
Solar
120 MWAgreement signed Chesterfield, VAPJM Dec 2018target 2027
Solar project AG2-583, Cumberland County
Solar · Boston Hill Solar, LLC
115 MWIn study Cumberland, VAPJM Jan 2025target 2026
Solar project AG2-441, Charlotte County
Solar · Virginia Electric and Power Company
113 MWIn study Charlotte, VAPJM Apr 2025target 2024
Solar project AI1-021, Pittsylvania County
Solar
105 MWIn study Pittsylvania, VAPJM Apr 2022target 2027
Hillandale Solar
Solar · Hillandale Solar, LLC
102 MWAgreement signed Pittsylvania, VAPJM Mar 2019target 2030
Solar project AI2-036, Augusta County
Solar
100 MWIn study Augusta, VAPJM Jan 2023target 2027
Gibson Solar I
Solar
100 MWAgreement signed King George, VAPJM Sep 2019target 2027
Blue Jay Solar
Solar
100 MWPaused / redesign Pulaski, VAPJM Mar 2018target 2025
Blue Rock Solar
Solar
100 MWAgreement signed Buckingham, VAPJM Mar 2019target 2026
Bakers Pond Solar
Solar
100 MWPaused / redesign Prince George, VAPJM Sep 2018target 2026
Solar project AG2-151, Cumberland County
Solar · Cumberland Solar, LLC
100 MWIn study Cumberland, VAPJM Feb 2025target 2024
Solar project AG2-068, Brunswick County
Solar · Virginia Electric and Power Company
100 MWIn study Brunswick, VAPJM Feb 2025target 2025
Dulles Solar and BESS
Solar
100 MWAgreement signed Loudoun, VAPJM Sep 2019target 2026
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)