United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Texas (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown285,821 MW
Active in queue1,797 MW5 requests
Agreement signed405 MW2 requests
Withdrawn285,821 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

28 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2014-018, Nacogdoches County
Gas
757 MWWithdrawn / abandoned Nacogdoches, TXSPP Jun 2014target 2018
Halyard Henderson
Gas Β· Halyard Energy
484 MWWithdrawn / abandoned Henderson, TXERCOT Mar 2014target 2021
Gas project GEN-2014-017, Nacogdoches County
Gas
477 MWWithdrawn / abandoned Nacogdoches, TXSPP Jun 2014target 2018
Onshore wind project GEN-2014-007, Floyd County
Onshore wind
400 MWWithdrawn / abandoned Floyd, TXSPP Mar 2014target 2016
Gas project J369, Newton County
Gas
393 MWWithdrawn / abandoned Newton, TXMISO May 2014target 2017
Gas project GEN-2014-067, Deaf Smith County
Gas
356 MWWithdrawn / abandoned Deaf Smith, TXSPP Sep 2014target 2019
Pumpkin Farm Wind
Onshore wind Β· Apex Clean
281 MWWithdrawn / abandoned Floyd, TXERCOT Feb 2014target 2020
RE Maplewood 2c Solar
Solar Β· Recurrent Energy
250 MWWithdrawn / abandoned Pecos, TXERCOT Oct 2014target 2021
Gas project GEN-2014-016, Nacogdoches County
Gas
227 MWWithdrawn / abandoned Nacogdoches, TXSPP Jun 2014target 2018
Gas project GEN-2014-012, Gaines County
Gas
225 MWWithdrawn / abandoned Gaines, TXSPP Mar 20142018
Gas project GEN-2014-068, Deaf Smith County
Gas
203 MWWithdrawn / abandoned Deaf Smith, TXSPP Sep 2014target 2019
Onshore wind project GEN-2014-073, Hale County
Onshore wind
200 MWWithdrawn / abandoned Hale, TXSPP Dec 2014target 2015
Onshore wind project GEN-2014-038, Hansford County
Onshore wind
200 MWWithdrawn / abandoned Hansford, TXSPP Sep 2014target 2017
Onshore wind project GEN-2014-074, Floyd County
Onshore wind
152 MWWithdrawn / abandoned Floyd, TXSPP Dec 2014target 2017
Chocolate Bayou Wind
Onshore wind Β· Engie
150 MWWithdrawn / abandoned Brazoria, TXERCOT Dec 2014target 2022
Onshore wind project GEN-2014-010, Deaf Smith County
Onshore wind
130 MWWithdrawn / abandoned Deaf Smith, TXSPP Mar 2014target 2016
Onshore wind project GEN-2014-054, Hockley County
Onshore wind
120 MWWithdrawn / abandoned Hockley, TXSPP Sep 2014target 2016
Solar project GEN-2014-029, Hale County
Solar
109 MWWithdrawn / abandoned Hale, TXSPP Sep 2014target 2016
RE Maplewood 2e Solar
Solar Β· Recurrent Energy
100 MWWithdrawn / abandoned Pecos, TXERCOT Oct 2014target 2020
Onshore wind project J429, Jefferson County
Onshore wind
100 MWWithdrawn / abandoned Jefferson, TXMISO Nov 2014target 2016
RE Maplewood 2d Solar
Solar Β· Recurrent Energy
100 MWWithdrawn / abandoned Pecos, TXERCOT Oct 2014target 2020
Onshore wind project GEN-2014-009, Bailey County
Onshore wind
83.7 MWWithdrawn / abandoned Bailey, TXSPP Mar 2014target 2016
Onshore wind project GEN-2014-053, Hockley County
Onshore wind
80.0 MWWithdrawn / abandoned Hockley, TXSPP Sep 2014target 2016
Solar project GEN-2014-043, Gaines County
Solar
80.0 MWWithdrawn / abandoned Gaines, TXSPP Sep 2014target 2016
Solar project GEN-2014-042, Hockley County
Solar
50.0 MWWithdrawn / abandoned Hockley, TXSPP Sep 2014target 2016
Solar project GEN-2014-044, Terry County
Solar
50.0 MWWithdrawn / abandoned Terry, TXSPP Sep 2014target 2016
Solar project J428, Jefferson County
Solar
50.0 MWWithdrawn / abandoned Jefferson, TXMISO Nov 2014target 2018
Onshore wind project GEN-2014-019, Ochiltree County
Onshore wind
15.0 MWWithdrawn / abandoned Ochiltree, TXSPP Jul 2014target 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)