United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Texas (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5414.9 GW
Active in queue28.9 GW115 requests
Agreement signed14.9 GW54 requests
Withdrawn558,621 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

54 requests · page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
BasRanch (TEF - Due Diligence)
Gas · CPV Basin Ranch, LLC
1,350 MWAgreement signed Ward, TXERCOT Aug 2020target 2028
Cedar Bayou 5 (TEF - Due Diligence)
Gas · NRG Cedar Bayou 5 LLC
697 MWAgreement signed Chambers, TXERCOT Mar 2020target 2027
Pinnington Solar
Solar + storage · Hecate Energy Longhorn Solar LLC
654 MWAgreement signed Jack, TXERCOT Dec 2020target 2026
Cachena Solar SLF
Solar + storage · Clear Fork Creek Solar LLC
601 MWAgreement signed Wilson, TXERCOT May 2020target 2027
Bottom Grass Solar
Solar + storage · Bottom Grass Solar Project, LLC
509 MWAgreement signed Colorado, TXERCOT Nov 2020target 2028
Duffy Solar
Solar + storage · VDA Solar Texas 1 LLC
503 MWAgreement signed Matagorda, TXERCOT Sep 2020target 2027
Baker Branch Solar
Solar · Mockingbird Solar Center, LLC
469 MWAgreement signed Lamar, TXERCOT Mar 2020target 2026
Sequoia II Solar
Solar · Deville Solar LLC
418 MWAgreement signed Callahan, TXERCOT Jan 2020target 2026
Caliche Mound Solar
Solar · Tierra Blanco Solar LLC
407 MWAgreement signed Deaf Smith, TXERCOT Jul 2020target 2026
Dorado Solar
Solar · Enbridge Solar (Sequoia I), LLC
401 MWAgreement signed Callahan, TXERCOT Jan 2020target 2026
Hanson Solar
Solar · Hanson Solar, LLC
399 MWAgreement signed Coleman, TXERCOT Oct 2020target 2027
Charger Solar
Solar · AP Solar 4, LLC
397 MWAgreement signed Refugio, TXERCOT Jun 2020target 2026
Tormes Solar
Solar · BDPU SOLAR TORMES LLC
357 MWAgreement signed Navarro, TXERCOT Oct 2020target 2027
Chillingham Solar
Solar · Chillingham Solar LLC
352 MWAgreement signed Bell, TXERCOT Aug 2020target 2026
Briggs Solar
Solar + storage · IP Quantum III, LLC
324 MWAgreement signed Haskell, TXERCOT Aug 2020target 2028
Solace Solar
Solar + storage · IP QUANTUM, LLC.
322 MWAgreement signed Haskell, TXERCOT Apr 2020target 2026
Cantaloupe Solar
Solar · Saragosa Del Sol Energy, LLC
307 MWAgreement signed Reeves, TXERCOT Dec 2020target 2028
Seine BESS
Battery storage · BRP Seine BESS LLC
301 MWAgreement signed Foard, TXERCOT Dec 2020target 2027
Solar project GEN-2020-054, Bowie County
Solar
298 MWAgreement signed Bowie, TXSPP Apr 2020target 2027
Fortuna Wind
Onshore wind · RWE Renewables Development, LLC
295 MWAgreement signed Jack, TXERCOT Mar 2020target 2026
Alila Solar
Solar + storage · Electra Energy Project, LLC
257 MWAgreement signed San Patricio, TXERCOT Oct 2020target 2028
Eval Storage
Battery storage · Hecate Grid East Valley Storage LLC
252 MWAgreement signed Cameron, TXERCOT Oct 2020target 2028
Tanglewood Solar
Solar · Brazoria Solar, LLC
251 MWAgreement signed Brazoria, TXERCOT Jul 2020target 2026
Samson Solar 3
Solar · Samson Solar Energy III LLC
250 MWAgreement signed Lamar, TXERCOT Jan 2020target 2026
Lavaca Bay Solar
Solar · Lavaca Bay Solar Project, LLC
244 MWAgreement signed Matagorda, TXERCOT Sep 2020target 2026
Solar project J1760, Liberty County
Solar
205 MWAgreement signed Liberty, TXMISO Jun 2020target 2023
Nockenut Springs Solar 2
Solar · Pecan Springs Energy, LLC
203 MWAgreement signed Guadalupe, TXERCOT Sep 2020target 2029
Nockenut Springs Solar 1
Solar · Pecan Springs Energy, LLC
203 MWAgreement signed Guadalupe, TXERCOT Sep 2020target 2029
Samson Solar 2
Solar · Samson Solar Energy II LLC
203 MWAgreement signed Lamar, TXERCOT Jan 2020target 2026
Erin Solar
Solar · Erin Solar LLC
203 MWAgreement signed Wharton, TXERCOT Jul 2020target 2028
Bottom Grass BESS
Solar + storage · Bottom Grass Solar Project, LLC
202 MWAgreement signed Colorado, TXERCOT Nov 2020target 2028
Donegal Solar
Solar · HE-Cottonwood Solar LLC
202 MWAgreement signed Dickens, TXERCOT Oct 2020target 2028
Soda Lake Solar 2 SLF
Solar + storage · Crane II Solar Electric, LLC
202 MWAgreement signed Crane, TXERCOT Sep 2020target 2027
Ramsey Storage
Battery storage · Hecate Energy Ramsey Storage LLC
201 MWAgreement signed Wharton, TXERCOT May 2020target 2027
Clutch City Solar Phase I
Solar · HZ Solar I, LLC
201 MWAgreement signed Brazoria, TXERCOT Jan 2020target 2028
Battery storage project GEN-2020-081, Rusk County
Battery storage
200 MWAgreement signed Rusk, TXSPP Apr 2020target 2028
Crowded Star Solar II
Solar + storage · Jones City Solar II, LLC
190 MWAgreement signed Jones, TXERCOT Mar 2020target 2026
Yellow Viking Solar
Solar · Yellow Viking Development One, LLC
171 MWAgreement signed Somervell, TXERCOT Oct 2020target 2027
Bowstring BESS
Battery storage · Longbow Energy Storage, LLC
155 MWAgreement signed San Patricio, TXERCOT Nov 2020target 2028
Anson BAT
Solar + storage · Anson II Storage LLC
154 MWAgreement signed Jones, TXERCOT Dec 2020target 2027
Pink Solar
Solar · Pink Solar, LLC
152 MWAgreement signed Hunt, TXERCOT Jan 2020target 2027
Stockyard Grid Batt
Battery storage · Stockyard Grid, LLC
151 MWAgreement signed Tarrant, TXERCOT Jan 2020target 2026
Starling Solar
Solar + storage · Starling Solar, LLC
144 MWAgreement signed Gonzales, TXERCOT Jun 2020target 2028
Shaw Solar
Solar · Rio Lago Solar, LLC
125 MWAgreement signed Bandera, TXERCOT Oct 2020target 2026
Caney Creek Solar
Solar · HEP Aquamarine Holdings LLC
121 MWAgreement signed Van Zandt, TXERCOT Sep 2020target 2027
Photon Solar 3 SLF
Solar · GulfStar Power, LLC
110 MWAgreement signed Wharton, TXERCOT Oct 2020target 2026
Blue Sky Sol
Solar + storage · Blue Sky Solar LLC
101 MWAgreement signed Crockett, TXERCOT Dec 2020target 2027
Matagorda Solar
Solar · Matagorda Solar Farm, LLC
101 MWAgreement signed Matagorda, TXERCOT May 2020target 2027
BRP Diran BESS
Battery storage · BRP Diran BESS LLC
101 MWAgreement signed Wharton, TXERCOT Dec 2020target 2028
Big Star Storage
Battery storage · RWE Solar Development, LLC
80.0 MWAgreement signed Bastrop, TXERCOT Jan 2020target 2026
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)